Old Total Allocation: 4217.44: New Total Allocation: 4217.44 : Task: 204 : Description: Cad Weld Joint for Rod-115

2021-10-02 13:58:00.722220
------------------Script Completed----------------------------

2021-10-02 13:58:49.986066
==================Script Sarted==========================

2021-10-02 13:58:49.991783
200 records selected

2021-10-02 13:58:50.53301
Old Total Allocation: 4217.44: New Total Allocation: 4217.44 : Task: 204 : Description: Cad Weld Joint for Rod-115

2021-10-02 13:58:53.733178
Old Total Allocation: 10800.00: New Total Allocation: 10000 : Task: 427 : Description: Refreshment

2021-10-02 13:58:55.881378
------------------Script Completed----------------------------

2021-10-02 13:59:41.707147
==================Script Sarted==========================

2021-10-02 13:59:41.723609
1000 records selected

2021-10-02 13:59:41.848212
Old Total Allocation: 75718.00: New Total Allocation: 71430.5 : Task: 430 : Description: Printing &amp; Stationery

2021-10-02 13:59:44.439175
Old Total Allocation: 12258.14: New Total Allocation: 11515.64 : Task: 491 : Description: Printing &amp; Stationery

2021-10-02 13:59:46.920167
Old Total Allocation: 46369.48: New Total Allocation: 45169.48 : Task: 521 : Description: Printing &amp; Stationery

2021-10-02 13:59:50.13987
Old Total Allocation: 670.44: New Total Allocation: 195.44 : Task: 528 : Description: Printing &amp; Stationery

2021-10-02 13:59:50.244479
Old Total Allocation: 55302.88: New Total Allocation: 52380.38 : Task: 545 : Description: Printing &amp; Stationery

2021-10-02 13:59:51.449870
Old Total Allocation: 10650.00: New Total Allocation: 13650 : Task: 642 : Description: Miscellaneous-Plumbing Work

2021-10-02 13:59:52.198885
Old Total Allocation: 5054.29: New Total Allocation: 3554.29 : Task: 694 : Description: Travelling/Transport

2021-10-02 13:59:52.343952
Old Total Allocation: 268285.91: New Total Allocation: 268285.91 : Task: 703 : Description: Printing Material

2021-10-02 13:59:52.427833
Old Total Allocation: 336450.00: New Total Allocation: 326500 : Task: 708 : Description: Toners for Ricoh printer

2021-10-02 13:59:53.129633
Old Total Allocation: 5002.95: New Total Allocation: 5002.95 : Task: 763 : Description: AC SPD-OBO Bettermann Germany

2021-10-02 13:59:53.221746
Old Total Allocation: 64805.22: New Total Allocation: 64805.22 : Task: 770 : Description: Earthing 

2021-10-02 13:59:53.254079
Old Total Allocation: 94708.34: New Total Allocation: 94708.34 : Task: 771 : Description: Installation Charges

2021-10-02 13:59:53.278730
Old Total Allocation: 421489.03: New Total Allocation: 421489.03 : Task: 772 : Description: Civil cost

2021-10-02 13:59:54.379105
Negative allocation found: -22900.00 : Task: 894 : Description: CEB/LECo Charges

2021-10-02 13:59:55.80146
Old Total Allocation: 23800.00: New Total Allocation: 1750 : Task: 949 : Description: Cad Weld Joint for Rod

2021-10-02 13:59:55.639937
Negative allocation found: -2.00 : Task: 993 : Description: Panel Boards

2021-10-02 13:59:55.655085
Old Total Allocation: 43826.13: New Total Allocation: 43826.13 : Task: 994 : Description: Nut &amp; Bolt, Hardware Items

2021-10-02 13:59:56.309087
Old Total Allocation: 295000.00: New Total Allocation: 307750 : Task: 1040 : Description: Floor tiling work

2021-10-02 13:59:56.355052
Old Total Allocation: 41700.00: New Total Allocation: 64200 : Task: 1043 : Description: Tile Skerting work

2021-10-02 13:59:56.397957
Old Total Allocation: 24400.00: New Total Allocation: 40200 : Task: 1046 : Description: Supplying and application of External wall painting-3 coat system

2021-10-02 13:59:57.8196
Old Total Allocation: 438285.11: New Total Allocation: 456631.36 : Task: 1084 : Description: Staff Welfare

2021-10-02 13:59:57.163926
Old Total Allocation: 0.00: New Total Allocation: 3900 : Task: 1094 : Description: Supplying and application of External wall painting-3 coat system

2021-10-02 13:59:57.639612
Negative allocation found: -20000.00 : Task: 1132 : Description: Office Maintenance

2021-10-02 13:59:57.877801
Old Total Allocation: 11579.00: New Total Allocation: 11359 : Task: 1151 : Description: Staff Welfare

2021-10-02 13:59:57.921344
Old Total Allocation: 4400.59: New Total Allocation: 2299.09 : Task: 1154 : Description: Printing &amp; Stationery

2021-10-02 13:59:58.90401
Old Total Allocation: 143244.50: New Total Allocation: 158874.5 : Task: 1161 : Description: Equipment Maintenance

2021-10-02 13:59:58.187913
Old Total Allocation: 128384.77: New Total Allocation: 128384.77 : Task: 1168 : Description: Printing &amp; Stationery

2021-10-02 13:59:58.516950
Old Total Allocation: 61913.44: New Total Allocation: 61868.44 : Task: 1193 : Description: Printing &amp; Stationery

2021-10-02 13:59:58.535585
Old Total Allocation: 54777.10: New Total Allocation: 54777.1 : Task: 1194 : Description: Consumables

2021-10-02 14:00:00.607890
Old Total Allocation: 341505.67: New Total Allocation: 341505.67 : Task: 1313 : Description: Point Wiring

2021-10-02 14:00:01.70696
Old Total Allocation: 30787.90: New Total Allocation: 30787.9 : Task: 1350 : Description: Power Cable-Kelani 16sqmm

2021-10-02 14:00:01.246753
Old Total Allocation: 7912.63: New Total Allocation: 7912.62 : Task: 1364 : Description: Nut &amp; Bolt, Hardware Items

2021-10-02 14:00:01.293710
Old Total Allocation: 3900.00: New Total Allocation: 2400 : Task: 1367 : Description: Travelling &amp; Transport

2021-10-02 14:00:01.586276
Negative allocation found: -3000.00 : Task: 1393 : Description: Lunch/Dinner

2021-10-02 14:00:01.613527
Old Total Allocation: 7916.35: New Total Allocation: 5057.35 : Task: 1395 : Description: Printing &amp; Stationery

2021-10-02 14:00:01.853403
Old Total Allocation: 84713.58: New Total Allocation: 74713.58 : Task: 1413 : Description: Equipment Maintenance

2021-10-02 14:00:01.943212
Old Total Allocation: 39825.18: New Total Allocation: 39535.18 : Task: 1420 : Description: Printing &amp; Stationery

2021-10-02 14:00:02.1788
Old Total Allocation: 631830.80: New Total Allocation: 643599.59 : Task: 1424 : Description: Equipment

2021-10-02 14:00:02.20650
Old Total Allocation: 420063.40: New Total Allocation: 424463.4 : Task: 1425 : Description: Computer, printers 

2021-10-02 14:00:02.507520
Old Total Allocation: 3016.29: New Total Allocation: 5200 : Task: 1452 : Description: Supply Electricity For Works

2021-10-02 14:00:02.943125
------------------Script Completed----------------------------

2021-10-02 14:06:35.12877
==================Script Sarted==========================

2021-10-02 14:06:35.68102
10000 records selected

2021-10-02 14:06:35.626456
Old Total Allocation: 37100.00: New Total Allocation: 106150 : Task: 1493 : Description: Shoring

2021-10-02 14:06:35.687478
Old Total Allocation: 1601800.00: New Total Allocation: 1651063.5 : Task: 1497 : Description: Labour cost sub

2021-10-02 14:06:35.856550
Old Total Allocation: 25000.00: New Total Allocation: 18750 : Task: 1510 : Description: Under the pile caps

2021-10-02 14:06:35.947981
Old Total Allocation: 280050.00: New Total Allocation: 370050 : Task: 1517 : Description: Material cost

2021-10-02 14:06:35.965519
Old Total Allocation: 2936100.00: New Total Allocation: 2981100 : Task: 1518 : Description: Material cost total

2021-10-02 14:06:36.161634
Old Total Allocation: 0.00: New Total Allocation: 99000 : Task: 1530 : Description: Surveyor Charges

2021-10-02 14:06:36.350440
Old Total Allocation: 3129992.27: New Total Allocation: 3184985.34 : Task: 1547 : Description: Point Wiring

2021-10-02 14:06:36.368562
Old Total Allocation: 138661.56: New Total Allocation: 173200.68 : Task: 1548 : Description: Switches and Socket outlets

2021-10-02 14:06:36.706629
Old Total Allocation: 1700.00: New Total Allocation: 850 : Task: 1571 : Description: Lugs &amp; Sleeves/gland

2021-10-02 14:06:36.726621
Old Total Allocation: 11064.29: New Total Allocation: 8129.29 : Task: 1572 : Description: Nut &amp; Bolt, Hardware Items

2021-10-02 14:06:36.858156
Old Total Allocation: 11500.00: New Total Allocation: 9500 : Task: 1582 : Description: Transport Charges

2021-10-02 14:06:36.875760
Old Total Allocation: 3530.00: New Total Allocation: 2810 : Task: 1583 : Description: Travelling &amp; Transport

2021-10-02 14:06:37.853066
Old Total Allocation: 319920.00: New Total Allocation: 320670 : Task: 1661 : Description: Sanitary Items

2021-10-02 14:06:38.6568
Old Total Allocation: 56200.00: New Total Allocation: 204200 : Task: 1674 : Description: Auditorium Structure

2021-10-02 14:06:38.360199
Old Total Allocation: 4250.00: New Total Allocation: 2250 : Task: 1702 : Description: Transport Charges

2021-10-02 14:06:38.748702
Negative allocation found: -2000.00 : Task: 1731 : Description: Stock Control

2021-10-02 14:06:39.29938
Old Total Allocation: 311000.00: New Total Allocation: 349000 : Task: 1746 : Description: Carpet flooring work

2021-10-02 14:06:39.569388
Old Total Allocation: 5138257.58: New Total Allocation: 5892832.58 : Task: 1784 : Description: Material Cost

2021-10-02 14:06:39.621717
Old Total Allocation: 0.00: New Total Allocation: 242500 : Task: 1788 : Description:  Construction of 225mm  Brick works 

2021-10-02 14:06:40.386750
Old Total Allocation: 5000.00: New Total Allocation: 155480 : Task: 1843 : Description: Reinforcement work

2021-10-02 14:06:40.667114
Old Total Allocation: 61898.32: New Total Allocation: 61898.32 : Task: 1865 : Description: DC SPD

2021-10-02 14:06:40.720183
Old Total Allocation: 2303.10: New Total Allocation: 1453.1 : Task: 1870 : Description: Surge Box -IP 67

2021-10-02 14:06:42.164858
Old Total Allocation: 36000.00: New Total Allocation: 106000 : Task: 1981 : Description: Socket and Spigot DI pipes

2021-10-02 14:06:43.127018
Old Total Allocation: 0.00: New Total Allocation: 125.47 : Task: 2055 : Description: Constructionof Gate Valve Chamber

2021-10-02 14:06:43.847705
Old Total Allocation: 282388.08: New Total Allocation: 282388.08 : Task: 2108 : Description: Point Wiring

2021-10-02 14:06:43.877354
Old Total Allocation: 16230.34: New Total Allocation: 16162.52 : Task: 2110 : Description: Switches and Socket outlets

2021-10-02 14:06:43.898722
Negative allocation found: -1355500.00 : Task: 2111 : Description: Light Fittings

2021-10-02 14:06:43.917599
Old Total Allocation: 87587.36: New Total Allocation: 56957.36 : Task: 2112 : Description: Conduits

2021-10-02 14:06:45.167686
Old Total Allocation: 31767.37: New Total Allocation: 31767.37 : Task: 2210 : Description: Water &amp; Electrical &amp; Security services

2021-10-02 14:06:45.231755
Old Total Allocation: 297807.62: New Total Allocation: 285500 : Task: 2215 : Description: Excavation-top soil for preservation

2021-10-02 14:06:45.249207
Old Total Allocation: 493252.98: New Total Allocation: 466400 : Task: 2216 : Description: Excavation-dying bed base 

2021-10-02 14:06:45.267236
Old Total Allocation: 446777.49: New Total Allocation: 424400 : Task: 2217 : Description: Excavation-wall foundation

2021-10-02 14:06:45.297102
Old Total Allocation: 3312975.00: New Total Allocation: 3325328.18 : Task: 2219 : Description: Concrete work-reinforced concrete dying bed walls

2021-10-02 14:06:45.338015
Old Total Allocation: 2777511.69: New Total Allocation: 2281397 : Task: 2222 : Description: wall

2021-10-02 14:06:45.368642
Old Total Allocation: 248545.37: New Total Allocation: 234000 : Task: 2224 : Description: for walls-chambers

2021-10-02 14:06:45.868343
Old Total Allocation: 134248.96: New Total Allocation: 131738.96 : Task: 2257 : Description: Printing &amp; Stationery

2021-10-02 14:06:46.231431
Old Total Allocation: 618406.00: New Total Allocation: 618446 : Task: 2282 : Description: Point Wiring

2021-10-02 14:06:46.286135
Old Total Allocation: 368758.61: New Total Allocation: 491696 : Task: 2284 : Description: Top layer with medium sand(0.5-1.5mm)

2021-10-02 14:06:46.316165
Old Total Allocation: 1615366.57: New Total Allocation: 1522500 : Task: 2286 : Description: Bottom layer with(25-40mm)Coarse Gravel

2021-10-02 14:06:46.396669
Old Total Allocation: 843880.20: New Total Allocation: 843880.2 : Task: 2292 : Description: Switches and Socket outlets

2021-10-02 14:06:49.342022
Old Total Allocation: 16874.99: New Total Allocation: 15474.99 : Task: 2501 : Description: Printing &amp; Stationery

2021-10-02 14:06:49.854635
Old Total Allocation: 84739.68: New Total Allocation: 84739.68 : Task: 2546 : Description: Point Wiring

2021-10-02 14:06:49.885793
Old Total Allocation: 198896.10: New Total Allocation: 198896.1 : Task: 2548 : Description: Switches and Socket outlets

2021-10-02 14:06:49.927139
Old Total Allocation: 250325.94: New Total Allocation: 250325.94 : Task: 2551 : Description: Conduits

2021-10-02 14:06:50.88942
Old Total Allocation: 91077.48: New Total Allocation: 91077.48 : Task: 2564 : Description: Labour

2021-10-02 14:06:50.300361
Old Total Allocation: 263925.00: New Total Allocation: 440575 : Task: 2581 : Description: Painting

2021-10-02 14:06:50.812045
Old Total Allocation: 3318.00: New Total Allocation: 2578 : Task: 2624 : Description: Food &amp; Lodging

2021-10-02 14:06:50.856078
Old Total Allocation: 6761.53: New Total Allocation: 6761.53 : Task: 2627 : Description: Miscellaneous

2021-10-02 14:06:53.816152
Old Total Allocation: 21225.84: New Total Allocation: 12252 : Task: 2862 : Description: Switches and Socket outlets

2021-10-02 14:06:54.827612
Old Total Allocation: 1238607.04: New Total Allocation: 523607.04 : Task: 2955 : Description: Alluminium Tape

2021-10-02 14:06:54.858853
Old Total Allocation: 41446.50: New Total Allocation: 23946.5 : Task: 2957 : Description: Cad Weld Joint for Others

2021-10-02 14:06:54.879992
Old Total Allocation: 959.64: New Total Allocation: 498.78 : Task: 2958 : Description: PVC Pipe

2021-10-02 14:06:55.527592
Old Total Allocation: 28138.92: New Total Allocation: 23899 : Task: 3004 : Description: Final Connection Items-Material

2021-10-02 14:06:55.949475
Old Total Allocation: 170838.52: New Total Allocation: 170838.52 : Task: 3036 : Description: Pipes-Material

2021-10-02 14:06:56.204382
Old Total Allocation: 2685049.78: New Total Allocation: 2685049.78 : Task: 3054 : Description: Plumbing Pipe Fittings &amp; Accessories-Material

2021-10-02 14:06:56.328570
Old Total Allocation: 2503357.16: New Total Allocation: 2544617.44 : Task: 3063 : Description:  Site management and supervision  

2021-10-02 14:06:56.539620
Old Total Allocation: 67004.75: New Total Allocation: 66961.75 : Task: 3076 : Description: Copper Tape 25*2.5mm-Material

2021-10-02 14:07:00.485385
Old Total Allocation: 41579.85: New Total Allocation: 43.5 : Task: 3364 : Description: Civil cost-Material

2021-10-02 14:07:01.439174
Old Total Allocation: 0.00: New Total Allocation: 375000 : Task: 3443 : Description: Lift up pumps for Tower 1,2 and 3-Material

2021-10-02 14:07:01.493869
Old Total Allocation: 0.00: New Total Allocation: 144000.01 : Task: 3447 : Description: Electro pit pumps for drain Pits-Material

2021-10-02 14:07:01.542825
Old Total Allocation: 26918.73: New Total Allocation: 26918.73 : Task: 3450 : Description: Kitchen sinks-Material

2021-10-02 14:07:01.568494
Old Total Allocation: 1293976.19: New Total Allocation: 1293976.19 : Task: 3451 : Description: Plumbing Pipe Fittings &amp; Accessories-Material

2021-10-02 14:07:01.605906
Old Total Allocation: 13200.00: New Total Allocation: 32700 : Task: 3453 : Description: Rain water havsting system acessories-Material

2021-10-02 14:07:01.735103
Old Total Allocation: 19950.00: New Total Allocation: 9450 : Task: 3463 : Description: Cad Weld Joint for Rod-Material

2021-10-02 14:07:01.754679
Old Total Allocation: 19950.00: New Total Allocation: 9450 : Task: 3464 : Description: Cad Weld Joint for Others-Material

2021-10-02 14:07:01.796369
Old Total Allocation: 240.00: New Total Allocation: 120 : Task: 3467 : Description: S/S Nut &amp; Bolt-Material

2021-10-02 14:07:02.121656
Old Total Allocation: 26600.00: New Total Allocation: 12600 : Task: 3482 : Description: Cad Weld Joint for Rod-Material

2021-10-02 14:07:02.186136
Old Total Allocation: 39900.00: New Total Allocation: 18900 : Task: 3483 : Description: Cad Weld Joint for Others-Material

2021-10-02 14:07:02.814656
Old Total Allocation: 4294.94: New Total Allocation: 4294.94 : Task: 3524 : Description: Other Fixing Accessories-Material

2021-10-02 14:07:03.88133
Old Total Allocation: 5079562.22: New Total Allocation: 4878296.34 : Task: 3543 : Description: Feeder Cable-Material

2021-10-02 14:07:03.184685
Old Total Allocation: 1842766.63: New Total Allocation: 1842766.63 : Task: 3547 : Description: Genaral Materials (Brackets, Nuts &amp; Bolts,Drop Anc-Material

2021-10-02 14:07:03.265804
Old Total Allocation: 0.00: New Total Allocation: 5718000 : Task: 3553 : Description: Jet fans, balance fans roof top fans-Material

2021-10-02 14:07:03.284668
Old Total Allocation: 27300.25: New Total Allocation: 24152.25 : Task: 3554 : Description: Cad Weld Joint for Rod-Material

2021-10-02 14:07:03.332101
Old Total Allocation: 3800.00: New Total Allocation: 1342800 : Task: 3557 : Description: Fire hose cabinets-Material

2021-10-02 14:07:04.402292
Old Total Allocation: 2499297.79: New Total Allocation: 2622724.19 : Task: 3631 : Description: Material-Material

2021-10-02 14:07:05.400018
Old Total Allocation: 30.00: New Total Allocation: 15 : Task: 3712 : Description: AC SPD-Material

2021-10-02 14:07:05.432404
Old Total Allocation: 6631.20: New Total Allocation: 4651.2 : Task: 3714 : Description: MCB-Material

2021-10-02 14:07:05.563983
Old Total Allocation: 39956.60: New Total Allocation: 968.73 : Task: 3720 : Description: Civil cost-Material

2021-10-02 14:07:05.619897
Old Total Allocation: 1508.00: New Total Allocation: 605.34 : Task: 3724 : Description: Other

2021-10-02 14:07:11.467146
Old Total Allocation: 998.00: New Total Allocation: 694 : Task: 4156 : Description: Copper Tape-Material

2021-10-02 14:07:11.497007
Old Total Allocation: 215491.12: New Total Allocation: 142691.12 : Task: 4158 : Description: Alluminium Tape-Material

2021-10-02 14:07:11.560855
Old Total Allocation: 11273.02: New Total Allocation: 4360.12 : Task: 4163 : Description: PVC Pipe-Material

2021-10-02 14:07:11.590819
Old Total Allocation: 64.00: New Total Allocation: 22 : Task: 4165 : Description: Rod-16*8*254-Material

2021-10-02 14:07:11.673411
Old Total Allocation: 2663.00: New Total Allocation: 3 : Task: 4171 : Description: Other Fixing Accessories-Material

2021-10-02 14:07:11.703063
Old Total Allocation: 21550.00: New Total Allocation: 10850 : Task: 4173 : Description: Labour-Labour

2021-10-02 14:07:12.424920
Negative allocation found: -498461.73 : Task: 4234 : Description: Inverter-Material

2021-10-02 14:07:12.571569
Old Total Allocation: 7113.60: New Total Allocation: 3161.6 : Task: 4244 : Description: MCB 16A-Material

2021-10-02 14:07:12.613000
Old Total Allocation: 95807.04: New Total Allocation: 31071.4 : Task: 4247 : Description: AC Cable -Material

2021-10-02 14:07:12.695259
Old Total Allocation: 20868.13: New Total Allocation: 20476.83 : Task: 4253 : Description: Civil cost-Material

2021-10-02 14:07:12.795125
Old Total Allocation: 83448.28: New Total Allocation: 41724.14 : Task: 4261 : Description: ABB WiFi Logger card-Material

2021-10-02 14:07:12.882874
Old Total Allocation: 3000.00: New Total Allocation: 1500 : Task: 4268 : Description: MC4 connectors-Material

2021-10-02 14:07:13.3635
Old Total Allocation: 9950.50: New Total Allocation: 5840 : Task: 4277 : Description: Earthing -Material

2021-10-02 14:07:13.36347
Old Total Allocation: 143372.34: New Total Allocation: 3074.24 : Task: 4279 : Description: Civil cost-Material

2021-10-02 14:07:14.161047
Old Total Allocation: 7100.00: New Total Allocation: 5600 : Task: 4352 : Description: Travelling &amp; Transport

2021-10-02 14:07:14.510197
Old Total Allocation: 5503886.92: New Total Allocation: 5560097 : Task: 4381 : Description: Total material cost-Material

2021-10-02 14:07:15.48379
Old Total Allocation: 324781.79: New Total Allocation: 324781.79 : Task: 4424 : Description: Point Wiring

2021-10-02 14:07:15.93920
Old Total Allocation: 78880.98: New Total Allocation: 57090 : Task: 4425 : Description: Switches and Socket outlets

2021-10-02 14:07:15.136070
Old Total Allocation: 57278.85: New Total Allocation: 57278.85 : Task: 4428 : Description: Feeder Cable

2021-10-02 14:07:15.196882
Old Total Allocation: 1491.07: New Total Allocation: 135.37 : Task: 4432 : Description: Earthing Materials

2021-10-02 14:07:15.250872
Old Total Allocation: 27870.00: New Total Allocation: 24870 : Task: 4435 : Description: Travelling &amp; Transport

2021-10-02 14:07:17.348816
Old Total Allocation: 3000.00: New Total Allocation: 1000 : Task: 4581 : Description: Transport Charges

2021-10-02 14:07:21.67877
Old Total Allocation: 4540.86: New Total Allocation: 4537.86 : Task: 4866 : Description: Rod 14.2*8*254-Material

2021-10-02 14:07:21.133197
Old Total Allocation: 3981.93: New Total Allocation: 3856.73 : Task: 4871 : Description: Other Fixing Accessories-Material

2021-10-02 14:07:21.713971
Old Total Allocation: 16.00: New Total Allocation: 6 : Task: 4919 : Description: Material-PVC Insulated Tape-Material

2021-10-02 14:07:22.744536
Old Total Allocation: 10043.53: New Total Allocation: 10043.53 : Task: 5001 : Description: Safety-Labour

2021-10-02 14:07:22.813430
Old Total Allocation: 66600.00: New Total Allocation: 123100 : Task: 5006 : Description: Concrete work

2021-10-02 14:07:22.931720
Old Total Allocation: 0.00: New Total Allocation: 54500 : Task: 5015 : Description: Concrete work

2021-10-02 14:07:23.696645
Old Total Allocation: 3110.00: New Total Allocation: 1690 : Task: 5076 : Description: Food &amp; Lodging

2021-10-02 14:07:24.11663
Old Total Allocation: 0.00: New Total Allocation: 44250 : Task: 5099 : Description: Supply and Installation UPVC Pipe And Fitiings

2021-10-02 14:07:24.30575
Old Total Allocation: 215514.52: New Total Allocation: 215514.52 : Task: 5100 : Description: Panel Boards

2021-10-02 14:07:24.133017
Old Total Allocation: 0.00: New Total Allocation: 25390 : Task: 5108 : Description: Metal Work (Hand Railing/ Ladders )

2021-10-02 14:07:24.457997
Old Total Allocation: 270000.00: New Total Allocation: 440000 : Task: 5128 : Description: Construction of Collecting chaimber

2021-10-02 14:07:24.573795
Old Total Allocation: 50000.00: New Total Allocation: 135000 : Task: 5134 : Description: Reinforced Concrete Grade 25 [1:1 1/2:3 (20)]&quot; In 

2021-10-02 14:07:25.484301
Old Total Allocation: 955099.79: New Total Allocation: 955099.79 : Task: 5201 : Description: Material

2021-10-02 14:07:25.717595
Old Total Allocation: 36246.80: New Total Allocation: 13015 : Task: 5220 : Description: Point Wiring

2021-10-02 14:07:26.268574
Old Total Allocation: 49144.98: New Total Allocation: 49144.98 : Task: 5262 : Description: Civil cost-material-Material

2021-10-02 14:07:26.974295
Old Total Allocation: 74603.70: New Total Allocation: 43103.7 : Task: 5309 : Description: Cad Weld Joint for Others-Material

2021-10-02 14:07:27.555302
Old Total Allocation: 75000.00: New Total Allocation: 143000 : Task: 5352 : Description: Supply and Installation DI Pipe and Fittings

2021-10-02 14:07:29.684486
Old Total Allocation: 1040.00: New Total Allocation: 490 : Task: 5494 : Description: Other Fixing Accessories-Material

2021-10-02 14:07:30.900187
Negative allocation found: -2200.00 : Task: 5585 : Description: Stock Control

2021-10-02 14:07:31.952872
Old Total Allocation: 30000.00: New Total Allocation: 30010 : Task: 5622 : Description: Light Fittings

2021-10-02 14:07:32.521741
Old Total Allocation: 15993.23: New Total Allocation: 4585.66 : Task: 5664 : Description: 16mm Tor bar

2021-10-02 14:07:32.566714
Old Total Allocation: 0.00: New Total Allocation: 291.89 : Task: 5667 : Description: 10mm Tor bar

2021-10-02 14:07:34.857463
Old Total Allocation: 8616.38: New Total Allocation: 8616.38 : Task: 5805 : Description: Nut &amp; Bolt, Hardware Items

2021-10-02 14:07:35.39666
Old Total Allocation: 880.00: New Total Allocation: 12100 : Task: 5820 : Description: Switches and Socket outlets

2021-10-02 14:07:35.80814
Old Total Allocation: 0.00: New Total Allocation: 850 : Task: 5823 : Description: Cable tray and ladders

2021-10-02 14:07:35.852110
Old Total Allocation: 1013650.00: New Total Allocation: 997600 : Task: 5887 : Description: Construction foundation(G25) and install the tower

2021-10-02 14:07:36.519426
Old Total Allocation: 886113.51: New Total Allocation: 891600 : Task: 5935 : Description: Supply &amp; lay G25 ready mix  concrete for 150 mm th

2021-10-02 14:07:36.561647
Old Total Allocation: 2234100.00: New Total Allocation: 2279100 : Task: 5937 : Description: Supply &amp; lay G25 ready mix  concrete for 100 mm th

2021-10-02 14:07:36.643892
Old Total Allocation: 170800.00: New Total Allocation: 163300 : Task: 5942 : Description: 225mm thk brick walls for existing doors and windo

2021-10-02 14:07:36.766417
Old Total Allocation: 427200.00: New Total Allocation: 421450 : Task: 5951 : Description: Supply and laying 8mm thick aluminium foil blanket

2021-10-02 14:07:37.208456
Old Total Allocation: 5588218.80: New Total Allocation: 6431098.8 : Task: 5983 : Description: PVC Pipes of PNT 7 (Type 600) &amp; (Type 1000)-Material

2021-10-02 14:07:37.241297
Old Total Allocation: 1213583.19: New Total Allocation: 3507783.19 : Task: 5985 : Description: Washout Valves -Material

2021-10-02 14:07:37.293577
Old Total Allocation: 8522205.44: New Total Allocation: 8845905.44 : Task: 5987 : Description: Laying &amp; Jointing in Trench Pipes, Specials &amp; Fitt-Material

2021-10-02 14:07:37.364168
Old Total Allocation: 1929905.73: New Total Allocation: 4515651.73 : Task: 5992 : Description: Construction of valve Chambers-Material

2021-10-02 14:07:37.508604
Old Total Allocation: 559489.02: New Total Allocation: 861646.32 : Task: 6001 : Description: Additional works

2021-10-02 14:07:38.654179
Old Total Allocation: 240866.00: New Total Allocation: 336158 : Task: 6086 : Description: Casting, Supplying &amp; erecting of &#039;Y&#039; type corner p

2021-10-02 14:07:38.689762
Old Total Allocation: 7113740.00: New Total Allocation: 7168240 : Task: 6088 : Description: Supply, Placing &amp; fixing of PVC coated chain link 

2021-10-02 14:07:38.868916
Old Total Allocation: 596300.00: New Total Allocation: 605100 : Task: 6098 : Description: Contingency Items &amp; Float

2021-10-02 14:07:39.317618
Old Total Allocation: 48750.00: New Total Allocation: 51600 : Task: 6134 : Description: Insurance

2021-10-02 14:07:39.382338
Old Total Allocation: 713850.00: New Total Allocation: 1024997 : Task: 6139 : Description: DI Pipe Work

2021-10-02 14:07:39.549153
Old Total Allocation: 9732810.00: New Total Allocation: 9945060 : Task: 6152 : Description: uPVC typePNT7, PNT11socket and spigot straight pip

2021-10-02 14:07:39.566706
Old Total Allocation: 29442.00: New Total Allocation: 28405 : Task: 6153 : Description: Furniture

2021-10-02 14:07:39.585050
Old Total Allocation: 962700.33: New Total Allocation: 1131075.33 : Task: 6154 : Description: Cost for Electrical Installation

2021-10-02 14:07:39.878810
Old Total Allocation: 156800.00: New Total Allocation: 287300 : Task: 6175 : Description: Material-Material

2021-10-02 14:07:41.325027
Old Total Allocation: 59919.54: New Total Allocation: 59919.54 : Task: 6284 : Description: Point Wiring

2021-10-02 14:07:41.394269
Old Total Allocation: 751413.36: New Total Allocation: 751413.36 : Task: 6289 : Description: Feeder Cable

2021-10-02 14:07:42.110174
Old Total Allocation: 27785.57: New Total Allocation: 27785.57 : Task: 6349 : Description: Nut &amp; Bolt, Hardware Items

2021-10-02 14:07:42.192145
Old Total Allocation: 409300.00: New Total Allocation: 2546000 : Task: 6355 : Description: Main Distribution boards

2021-10-02 14:07:43.208920
Old Total Allocation: 47659.66: New Total Allocation: 39.92 : Task: 6429 : Description: 16mm Tor bar-Material

2021-10-02 14:07:43.260297
Old Total Allocation: 0.00: New Total Allocation: 5.68 : Task: 6431 : Description: 10mm Tor bar-Material

2021-10-02 14:07:43.508076
Old Total Allocation: 159318.75: New Total Allocation: 256418.75 : Task: 6448 : Description: Supply and Installation DI Pipe and Fittings

2021-10-02 14:07:43.527945
Old Total Allocation: 162655.00: New Total Allocation: 183330 : Task: 6449 : Description: Supply and Installation DI Pipe and Fittings

2021-10-02 14:07:43.688231
Negative allocation found: -25200.00 : Task: 6461 : Description: Cad Weld Joint for Rod-Material

2021-10-02 14:07:44.257281
Old Total Allocation: 288968.95: New Total Allocation: 462268.95 : Task: 6504 : Description: Miscellaneous

2021-10-02 14:07:45.825506
Old Total Allocation: 1680.46: New Total Allocation: 1680.46 : Task: 6618 : Description: Civil cost-Material

2021-10-02 14:07:49.509207
Old Total Allocation: 46552.80: New Total Allocation: 46552.8 : Task: 6913 : Description: Civil cost-Material

2021-10-02 14:07:50.709603
Negative allocation found: -40000.00 : Task: 7010 : Description: Concrete work-Material

2021-10-02 14:07:52.7189
Old Total Allocation: 429120.00: New Total Allocation: 337320 : Task: 7093 : Description: Tower erection and tower painting 

2021-10-02 14:07:52.143599
Negative allocation found: -9860.00 : Task: 7102 : Description: 10mm Tor bar

2021-10-02 14:07:52.815247
Old Total Allocation: 273150.00: New Total Allocation: 315650 : Task: 7155 : Description: Floor Finishing-Material

2021-10-02 14:07:53.431586
Old Total Allocation: 64500.00: New Total Allocation: 134500 : Task: 7202 : Description: uPVC double socketed bends suitable for mechanical

2021-10-02 14:07:53.512161
Old Total Allocation: 8200.00: New Total Allocation: 80200 : Task: 7208 : Description: valves &amp; fittings required for WASHOUT VALVE

2021-10-02 14:07:53.563278
Old Total Allocation: 0.00: New Total Allocation: 40000 : Task: 7210 : Description: valves &amp; fittings required for AIR VALVE complete-

2021-10-02 14:07:53.625547
Old Total Allocation: 14700.00: New Total Allocation: 471850 : Task: 7211 : Description:  Culvert crossings - Type A

2021-10-02 14:07:53.673044
Old Total Allocation: 28000.00: New Total Allocation: 1636140 : Task: 7213 : Description: Culvert crossings - Type D

2021-10-02 14:07:53.693085
Old Total Allocation: 0.00: New Total Allocation: 136857.6 : Task: 7214 : Description: Culvert crossings - Type F

2021-10-02 14:07:53.711409
Old Total Allocation: 250000.00: New Total Allocation: 394000 : Task: 7215 : Description: BRIDGE CROSSINGS

2021-10-02 14:07:54.349284
Old Total Allocation: 1143292.07: New Total Allocation: 1172815.2 : Task: 7262 : Description: Air Valve Chamber - (excluding the fittings menti

2021-10-02 14:07:54.383518
Old Total Allocation: 457350.00: New Total Allocation: 469350 : Task: 7264 : Description: Construction of Surface Box complete for the inlin

2021-10-02 14:07:54.426939
Old Total Allocation: 50000.00: New Total Allocation: 60200 : Task: 7267 : Description: Culvert crossings - Type D

2021-10-02 14:07:55.534656
Negative allocation found: -153600.00 : Task: 7351 : Description: Additional Light Fitting Works

2021-10-02 14:07:55.615821
Old Total Allocation: 469600.00: New Total Allocation: 489000 : Task: 7357 : Description: Provide &amp; Maintaining Office Facilities ,Staff Facilities, Temperay storers, Meting rooms

2021-10-02 14:07:55.711413
Old Total Allocation: 155000.00: New Total Allocation: 243650 : Task: 7364 : Description: Surveying and preparation of LS drawings setting 

2021-10-02 14:07:55.742859
Old Total Allocation: 12000.00: New Total Allocation: 263600 : Task: 7366 : Description: Air Valves

2021-10-02 14:07:55.953975
Old Total Allocation: 9913.47: New Total Allocation: 9913.47 : Task: 7383 : Description: Other Fixing Accessories (DIRECT)-Material

2021-10-02 14:07:56.397955
Old Total Allocation: 115554.64: New Total Allocation: 115554.64 : Task: 7416 : Description: Feeder Cable

2021-10-02 14:07:56.545460
Old Total Allocation: 22820.09: New Total Allocation: 22820.09 : Task: 7428 : Description: Nut &amp; Bolt, Hardware Items

2021-10-02 14:07:56.640647
Old Total Allocation: 16141.13: New Total Allocation: 16141.13 : Task: 7433 : Description: Testing &amp; Commissioning

2021-10-02 14:07:56.993025
Negative allocation found: -63000.00 : Task: 7459 : Description: Cad Weld Joint for Rod-Material

2021-10-02 14:07:57.693471
Old Total Allocation: 2098.29: New Total Allocation: 2098.3 : Task: 7507 : Description: Civil cost-Material

2021-10-02 14:07:58.217244
Old Total Allocation: 2995804.41: New Total Allocation: 3709435 : Task: 7549 : Description: Reinstatement

2021-10-02 14:07:59.497164
Old Total Allocation: 0.00: New Total Allocation: 1850 : Task: 7651 : Description: Steel work

2021-10-02 14:07:59.616434
Old Total Allocation: 379000.00: New Total Allocation: 406200 : Task: 7659 : Description: Pipe works

2021-10-02 14:07:59.725303
Old Total Allocation: 60500.00: New Total Allocation: 203000 : Task: 7667 : Description: Roof ceiling

2021-10-02 14:07:59.792932
Old Total Allocation: 28117.50: New Total Allocation: 450 : Task: 7672 : Description: Electrical installation

2021-10-02 14:07:59.963923
Old Total Allocation: 36000.00: New Total Allocation: 57000 : Task: 7682 : Description: In-Situ concrete

2021-10-02 14:08:00.44414
Old Total Allocation: 10939.00: New Total Allocation: 5754 : Task: 7688 : Description: Electrical works

2021-10-02 14:08:00.122895
Old Total Allocation: 0.00: New Total Allocation: 14504 : Task: 7694 : Description: 16x200mm U Bolt

2021-10-02 14:08:00.141230
Old Total Allocation: 0.00: New Total Allocation: 43350 : Task: 7695 : Description: 40x6mm Flat Iron - Lenght 5800mm-Material

2021-10-02 14:08:00.177952
Old Total Allocation: 0.00: New Total Allocation: 64800 : Task: 7697 : Description: 12x50mm Nut &amp; Bolt (full third)-Material

2021-10-02 14:08:00.247409
Old Total Allocation: 0.00: New Total Allocation: 13690 : Task: 7702 : Description: 12x125mm U Bolt-Material

2021-10-02 14:08:00.266178
Old Total Allocation: 0.00: New Total Allocation: 17760 : Task: 7703 : Description: 16x132mm C Bolt-Material

2021-10-02 14:08:00.283526
Old Total Allocation: 0.00: New Total Allocation: 17200 : Task: 7704 : Description: 16x117mm C Bolt-Material

2021-10-02 14:08:00.312507
Old Total Allocation: 0.00: New Total Allocation: 1368 : Task: 7706 : Description: Uncommon Budget Items12x40mm Nut &amp; Bolt (third 40m-Material

2021-10-02 14:08:00.331801
Old Total Allocation: 0.00: New Total Allocation: 35600 : Task: 7707 : Description: 12x170mm Box Bolt-Material

2021-10-02 14:08:00.373563
Old Total Allocation: 0.00: New Total Allocation: 3176 : Task: 7710 : Description: 12x65mm Bolt with Nut  (full third)-Material

2021-10-02 14:08:00.391905
Old Total Allocation: 0.00: New Total Allocation: 13690 : Task: 7711 : Description: 12x125mm U Bolt-Material

2021-10-02 14:08:00.410346
Old Total Allocation: 0.00: New Total Allocation: 5328 : Task: 7712 : Description: 12x80mm Nut &amp; Bolt (third 40mm)-Material

2021-10-02 14:08:00.883987
Old Total Allocation: 900800.00: New Total Allocation: 968300 : Task: 7749 : Description: Labour cost for Construction of P.V.C. &amp; D.I Pipe 

2021-10-02 14:08:00.989550
Old Total Allocation: 150000.00: New Total Allocation: 178000 : Task: 7757 : Description: Allow for Scaffolding and Other	

2021-10-02 14:08:01.33083
Negative allocation found: -14844.78 : Task: 7760 : Description: Point Wiring

2021-10-02 14:08:01.86940
Negative allocation found: -10000.00 : Task: 7762 : Description: Panel Boards

2021-10-02 14:08:01.106110
Negative allocation found: -641740.00 : Task: 7763 : Description: Feeder Cable

2021-10-02 14:08:01.171466
Old Total Allocation: 2051.18: New Total Allocation: 2051.18 : Task: 7767 : Description: Material-Material

2021-10-02 14:08:01.885101
Old Total Allocation: 0.00: New Total Allocation: 72000 : Task: 7820 : Description: M16 U bolt-Material

2021-10-02 14:08:01.904157
Old Total Allocation: 0.00: New Total Allocation: 30000 : Task: 7821 : Description: M12 U bolt-Material

2021-10-02 14:08:01.983865
Old Total Allocation: 0.00: New Total Allocation: 860 : Task: 7827 : Description: M 12x100mm U bolt-Material

2021-10-02 14:08:02.4192
Old Total Allocation: 0.00: New Total Allocation: 4160 : Task: 7828 : Description: M 16 x330mm rod-Material

2021-10-02 14:08:02.51678
Old Total Allocation: 0.00: New Total Allocation: 18000 : Task: 7831 : Description: M 16 U Bolt - 114mm GI pipe-Material

2021-10-02 14:08:02.105846
Old Total Allocation: 0.00: New Total Allocation: 4160 : Task: 7832 : Description: M16x400mm Nut &amp; bolt-Material

2021-10-02 14:08:02.162065
Old Total Allocation: 0.00: New Total Allocation: 8800 : Task: 7835 : Description: 12mmx155mm J bolt-Material

2021-10-02 14:08:02.241772
Old Total Allocation: 0.00: New Total Allocation: 10320 : Task: 7838 : Description: 10x40 Nut &amp; Bolt-Material

2021-10-02 14:08:02.271474
Old Total Allocation: 0.00: New Total Allocation: 2080 : Task: 7839 : Description: 10mm tor steel-Material

2021-10-02 14:08:02.314978
Old Total Allocation: 0.00: New Total Allocation: 9000 : Task: 7842 : Description: 12x170mm U Bolt -Material

2021-10-02 14:08:02.334816
Old Total Allocation: 0.00: New Total Allocation: 23625 : Task: 7843 : Description: 12x180mm U Bolt -Material

2021-10-02 14:08:02.352296
Old Total Allocation: 0.00: New Total Allocation: 3000 : Task: 7844 : Description: 12x200mm U Bolt -Material

2021-10-02 14:08:02.370796
Old Total Allocation: 0.00: New Total Allocation: 6000 : Task: 7845 : Description: 12x300mm U Bolt -Material

2021-10-02 14:08:02.388487
Old Total Allocation: 0.00: New Total Allocation: 58125 : Task: 7846 : Description: 12x150mm U Bolt -Material

2021-10-02 14:08:02.406615
Old Total Allocation: 0.00: New Total Allocation: 344 : Task: 7847 : Description: 12x100mm Nut &amp; Bolt -Material

2021-10-02 14:08:02.426041
Old Total Allocation: 0.00: New Total Allocation: 860 : Task: 7848 : Description: 12x50  mm Nut &amp; Bolt -Material

2021-10-02 14:08:02.456091
Old Total Allocation: 0.00: New Total Allocation: 258 : Task: 7850 : Description: 12x70mm Nut &amp; Bolt -Material

2021-10-02 14:08:02.475433
Old Total Allocation: 0.00: New Total Allocation: 1978 : Task: 7851 : Description: 12x75mm Nut &amp; Bolt -Material

2021-10-02 14:08:02.495436
Old Total Allocation: 0.00: New Total Allocation: 7680 : Task: 7852 : Description: V Bolt 100x150mm-Material

2021-10-02 14:08:02.534541
Old Total Allocation: 0.00: New Total Allocation: 1376 : Task: 7854 : Description: 12x65mm Nut &amp; Bolt -Material

2021-10-02 14:08:02.559485
Old Total Allocation: 0.00: New Total Allocation: 6650 : Task: 7855 : Description: 110x110x6mm L Angle-Material

2021-10-02 14:08:03.47016
Negative allocation found: -4000.00 : Task: 7892 : Description: Meal Allowance

2021-10-02 14:08:03.381608
Old Total Allocation: 719.00: New Total Allocation: 1239 : Task: 7915 : Description: Safety Net Installation with necessary Gi Pipe Str-Material

2021-10-02 14:08:03.439491
Old Total Allocation: 862492.33: New Total Allocation: 1047495 : Task: 7919 : Description: First floor  To Second floor level

2021-10-02 14:08:03.459246
Old Total Allocation: 63712.41: New Total Allocation: 364188 : Task: 7920 : Description: Third Floor to Forth Floor

2021-10-02 14:08:03.478222
Old Total Allocation: 135336.11: New Total Allocation: 443840 : Task: 7921 : Description: Third Floor to Forth Floor

2021-10-02 14:08:03.537937
Old Total Allocation: 1976.82: New Total Allocation: 1976.82 : Task: 7925 : Description: Copper Tape-Material

2021-10-02 14:08:03.613735
Old Total Allocation: 40598.53: New Total Allocation: 218500 : Task: 7929 : Description: Fourt Floor to Fifth Floor

2021-10-02 14:08:03.915479
Old Total Allocation: 0.00: New Total Allocation: 826500 : Task: 7948 : Description: DPC to First floor level

2021-10-02 14:08:03.934531
Old Total Allocation: 1021985.56: New Total Allocation: 1186530 : Task: 7949 : Description: Masonry works

2021-10-02 14:08:03.953244
Old Total Allocation: 345147.13: New Total Allocation: 331555 : Task: 7950 : Description: 16mm thk internal plastering on brick walls in cem

2021-10-02 14:08:04.122
Old Total Allocation: 320753.98: New Total Allocation: 396684.03 : Task: 7953 : Description: Provitional sums

2021-10-02 14:08:04.752453
Old Total Allocation: 0.00: New Total Allocation: 36800 : Task: 8002 : Description: 16x175mm U Bolt-Material

2021-10-02 14:08:04.810856
Old Total Allocation: 0.00: New Total Allocation: 18400 : Task: 8006 : Description: M16 U bolt-Material

2021-10-02 14:08:04.842161
Old Total Allocation: 0.00: New Total Allocation: 36801 : Task: 8008 : Description: M16 C bolt-Material

2021-10-02 14:08:04.861898
Old Total Allocation: 4160.00: New Total Allocation: 8320 : Task: 8009 : Description: M16x400mm Nut &amp; bolt-Material

2021-10-02 14:08:04.879321
Old Total Allocation: 0.00: New Total Allocation: 4160 : Task: 8010 : Description: M16x310mm Nut &amp; bolt-Material

2021-10-02 14:08:05.545815
Negative allocation found: -1914547.30 : Task: 8060 : Description: 325W Canadian Solar Module-Material

2021-10-02 14:08:05.719978
Old Total Allocation: 1999.99: New Total Allocation: 2000 : Task: 8074 : Description: Other-Material

2021-10-02 14:08:06.4599
Old Total Allocation: 77993.60: New Total Allocation: 77993.6 : Task: 8097 : Description: Site office &amp; stores

2021-10-02 14:08:06.96056
Old Total Allocation: 18345.83: New Total Allocation: 15750 : Task: 8104 : Description: Water &amp; Elec. supply

2021-10-02 14:08:06.482284
Old Total Allocation: 1653388.65: New Total Allocation: 1687138.65 : Task: 8135 : Description: Labour cost for civil works-Labour

2021-10-02 14:08:06.503362
Old Total Allocation: 841810.10: New Total Allocation: 782244.98 : Task: 8136 : Description: Cost for Metal works

2021-10-02 14:08:06.547827
Old Total Allocation: 1172314.00: New Total Allocation: 1188064 : Task: 8139 : Description: Cost for mechanical Installation

2021-10-02 14:08:06.629819
Old Total Allocation: 3377313.43: New Total Allocation: 3652340.85 : Task: 8144 : Description: Cost for Civil Materials as per the B.O.Q

2021-10-02 14:08:07.64277
Old Total Allocation: 608064.85: New Total Allocation: 608064.85 : Task: 8174 : Description: Cable tray and ladders

2021-10-02 14:08:07.152568
Old Total Allocation: 1177513.43: New Total Allocation: 1177513.43 : Task: 8178 : Description: Feeder Cable

2021-10-02 14:08:07.191401
Old Total Allocation: 1648125.00: New Total Allocation: 2226345 : Task: 8180 : Description: Preliminaries

2021-10-02 14:08:07.383612
Old Total Allocation: 6328.12: New Total Allocation: 6328.12 : Task: 8194 : Description: Tools

2021-10-02 14:08:10.844167
Negative allocation found: -569184.00 : Task: 8476 : Description: Copper Tape-Material

2021-10-02 14:08:12.115657
Old Total Allocation: 0.00: New Total Allocation: 7100 : Task: 8581 : Description: 110x110x6mm L Angle-Length-Material

2021-10-02 14:08:12.313558
Old Total Allocation: 7083.00: New Total Allocation: 18083 : Task: 8597 : Description: Concrete work including form work &amp; reinforcement

2021-10-02 14:08:12.752190
Old Total Allocation: 217764.79: New Total Allocation: 221114.79 : Task: 8628 : Description: Conduits

2021-10-02 14:08:12.821293
Old Total Allocation: 26801.90: New Total Allocation: 25913.25 : Task: 8633 : Description: Nut &amp; Bolt, Hardware Items

2021-10-02 14:08:13.388798
Old Total Allocation: 717152.03: New Total Allocation: 891830 : Task: 8675 : Description: MISCELLANEOUS WORK-Material

2021-10-02 14:08:13.470049
Old Total Allocation: 154276.53: New Total Allocation: 167497.53 : Task: 8681 : Description: Supply and Installation DI Pipe and Fittings-Material

2021-10-02 14:08:13.805048
Negative allocation found: -5000.00 : Task: 8707 : Description: Transport without Mild steel/DC-Indirect Costs

2021-10-02 14:08:14.998599
Negative allocation found: -13466.25 : Task: 8793 : Description: 6mm AC Cable(2C)-Material

2021-10-02 14:08:16.62705
Old Total Allocation: 21844.51: New Total Allocation: 21844.51 : Task: 8878 : Description: DLSF 8A-Material

2021-10-02 14:08:19.954653
Old Total Allocation: 7830.87: New Total Allocation: 7830.87 : Task: 9172 : Description: Civil cost-Material

2021-10-02 14:08:21.67780
Old Total Allocation: 16215113.27: New Total Allocation: 16284142.25 : Task: 9262 : Description: Supply and Installation DI Pipe and Fittings-Material

2021-10-02 14:08:21.420868
Old Total Allocation: 5222.32: New Total Allocation: 5222.32 : Task: 9291 : Description: Other Fixing Accessories-Material

2021-10-02 14:08:22.978602
Old Total Allocation: 63395.00: New Total Allocation: 157595 : Task: 9414 : Description: PVC Pipes Maker Tape without Enclosed Aluminium T-Material

2021-10-02 14:08:23.111938
Old Total Allocation: 20802.33: New Total Allocation: 20802.33 : Task: 9425 : Description: AC Cable -Material

2021-10-02 14:08:26.376681
Old Total Allocation: 1440580.00: New Total Allocation: 3354450 : Task: 9677 : Description: PIPE WORK- FITTINGS AND VALVES

2021-10-02 14:08:26.409038
Old Total Allocation: 38060.00: New Total Allocation: 47960 : Task: 9679 : Description: SCOUR VALVES

2021-10-02 14:08:26.438113
Old Total Allocation: 2358756.95: New Total Allocation: 2589438.79 : Task: 9681 : Description: PIPE WORK MANHOLES AND PIPEWORK ANCILLARIES

2021-10-02 14:08:26.697686
Old Total Allocation: 1747072.75: New Total Allocation: 1922592.75 : Task: 9702 : Description: PIPEWORK - SUPPORT AND PROTECTION, ANCILLARIES TO 

2021-10-02 14:08:27.865209
Old Total Allocation: 2495.28: New Total Allocation: 2495.28 : Task: 9798 : Description: Other Fixing Accessories-Material

2021-10-02 14:08:30.334472
Old Total Allocation: 2203181.85: New Total Allocation: 2862699.94 : Task: 9992 : Description: Reinforcement

2021-10-02 14:08:30.763600
Negative allocation found: -293493.31 : Task: 10027 : Description: Copper Tape-Material

2021-10-02 14:08:30.841006
Negative allocation found: -101131.68 : Task: 10033 : Description: Earth Cable-Material

2021-10-02 14:08:31.691913
Negative allocation found: -5306630.22 : Task: 10102 : Description: Solar Module-Material

2021-10-02 14:08:32.222408
Old Total Allocation: 78064.47: New Total Allocation: 77106 : Task: 10141 : Description: Allow for maintaining of temporary site office, stores, yards, sanitary facilities for the contractor.
-Material

2021-10-02 14:08:32.403497
Old Total Allocation: 591868.96: New Total Allocation: 608100 : Task: 10153 : Description: Allow for supplying temporary electricity for the work during the Construction including temporary connection, distribution system for the work, internal arrangements and all payment to the authorities for temporary  connection. In case of the main supply is not available or not adequate the contractor to provide alternative supply to the works.


2021-10-02 14:08:32.504321
Old Total Allocation: 2189345.00: New Total Allocation: 2180422 : Task: 10154 : Description: llow for payments for consumption of electricity including providing alternate supply if necessary.

2021-10-02 14:08:32.528164
Old Total Allocation: 209030.94: New Total Allocation: 211500 : Task: 10155 : Description: llow for payments for consumption of electricity including providing alternate supply if necessary.


2021-10-02 14:08:32.560809
Old Total Allocation: 1321073.56: New Total Allocation: 1307134 : Task: 10157 : Description: Allow for consumption of water including providing alternate supply if necessary.


2021-10-02 14:08:32.592221
Old Total Allocation: 287614.74: New Total Allocation: 200850 : Task: 10159 : Description: Allow for necessary barricades, railing, temporary walk ways, protective netting, fencing, hoarding and screens around the site boundaries and  other precautions at site for the protection work, adjoining properties and public to the required standard and to the approval of the Engineer. The Contractor shall submit the details of his proposal to the Engineer for approval.
-Material

2021-10-02 14:08:32.611058
Old Total Allocation: 899000.00: New Total Allocation: 1499000 : Task: 10160 : Description: Allow for shifting and maintaining of barricades, railing  -do-,
-Labour

2021-10-02 14:08:32.641895
Old Total Allocation: 100000.00: New Total Allocation: 115000 : Task: 10162 : Description: Allow for necessary lighting, watchmen, protection of work and any materials with suitable security measures during construction until handing over.


2021-10-02 14:08:32.665937
Old Total Allocation: 43108.97: New Total Allocation: 43000 : Task: 10163 : Description: Allow for necessary lighting, watchmen, protection of work and any materials with suitable security measures during construction until handing over.
-Labour

2021-10-02 14:08:32.756189
Old Total Allocation: 7621.77: New Total Allocation: 7621.77 : Task: 10170 : Description: Rod-Material

2021-10-02 14:08:33.165225
Old Total Allocation: 60000.00: New Total Allocation: 92500 : Task: 10197 : Description: Allow for design and establish a suitable dewateri-Material

2021-10-02 14:08:33.245476
Old Total Allocation: 662450.00: New Total Allocation: 707000 : Task: 10203 : Description: Small Tools &amp; Tools Maintenance-Tool

2021-10-02 14:08:33.843567
Old Total Allocation: 380665.80: New Total Allocation: 407044 : Task: 10250 : Description:  Allow for establishment of tower crane, -Material

2021-10-02 14:08:34.452456
Old Total Allocation: 271710.56: New Total Allocation: 272750 : Task: 10258 : Description: Allow for safety measures and equipment&#039;s-Material

2021-10-02 14:08:34.471267
Old Total Allocation: 46500.00: New Total Allocation: 41550 : Task: 10259 : Description: Allow for protection of public and private services. The Contractor shall protect, uphold and maintain all water and drain pipes, ducts, sewers, service mains, overhead cables, etc., unless earmarked for demolition, during the execution of the works. The Contractor is to make good any damage due to any cause within his control at his own expenses or pay any cost and charges in connection therewith. In cases where the services are to be temporarily terminated or diverted the Contractor is to give-Labour

2021-10-02 14:08:35.118063
Negative allocation found: -7786.25 : Task: 10308 : Description: Copper Tape-Material

2021-10-02 14:08:37.320409
Old Total Allocation: 167807.00: New Total Allocation: 180807 : Task: 10477 : Description: Excavation

2021-10-02 14:08:37.776421
Old Total Allocation: 278006.00: New Total Allocation: 551006 : Task: 10515 : Description: External Walls - 200 mm thick block wall in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centers)- Ground floor-Material

2021-10-02 14:08:37.804848
Old Total Allocation: 120549.46: New Total Allocation: 129633 : Task: 10517 : Description: External Walls - 200 mm thick block wall in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centers)- First floor-Material

2021-10-02 14:08:37.837389
Old Total Allocation: 135500.00: New Total Allocation: 248200 : Task: 10519 : Description: External Walls - 200 mm thick block wall in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centers)- Second floor-Material

2021-10-02 14:08:37.889484
Old Total Allocation: 360500.00: New Total Allocation: 523220 : Task: 10523 : Description: External Walls - 200 mm thick block wall in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centers)- Fourth floor-Material

2021-10-02 14:08:37.918259
Old Total Allocation: 205372.00: New Total Allocation: 548132 : Task: 10525 : Description: External Walls - 200 mm thick block wall in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centers)- Fifth floor-Material

2021-10-02 14:08:37.948368
Old Total Allocation: 79000.00: New Total Allocation: 202000 : Task: 10527 : Description: External Walls - 200 mm thick block wall in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centers)- Sixth floor-Material

2021-10-02 14:08:37.978113
Old Total Allocation: 96639.65: New Total Allocation: 707425 : Task: 10529 : Description: External Walls - 200 mm thick block wall in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centers)- Seventh floor-Material

2021-10-02 14:08:38.7122
Old Total Allocation: 10083.02: New Total Allocation: 179900 : Task: 10531 : Description: External Walls - 200 mm thick block wall in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centers)- Eighth floor-Material

2021-10-02 14:08:38.36595
Old Total Allocation: 596161.17: New Total Allocation: 589137 : Task: 10533 : Description: External Walls - 200 mm thick block wall in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centers)- Ninth floor-Material

2021-10-02 14:08:38.68718
Old Total Allocation: 197174.00: New Total Allocation: 228109 : Task: 10535 : Description: External Walls - 200 mm thick block wall in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centers)- Tength floor-Material

2021-10-02 14:08:38.242241
Old Total Allocation: 70000.00: New Total Allocation: 115000 : Task: 10549 : Description:  Internal Walls - 100 mm thick block walls in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centres)- Ground floor-Material

2021-10-02 14:08:38.295990
Old Total Allocation: 82746.00: New Total Allocation: 398146 : Task: 10553 : Description: Internal Walls - 100 mm thick block walls in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centres)- Third Floor-Material

2021-10-02 14:08:38.326809
Old Total Allocation: 224161.11: New Total Allocation: 275350 : Task: 10555 : Description: Internal Walls - 100 mm thick block walls in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centres)- Fourth Floor-Material

2021-10-02 14:08:38.362931
Old Total Allocation: 101131.00: New Total Allocation: 106651 : Task: 10557 : Description: Internal Walls - 100 mm thick block walls in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centres)- Fifth Floor-Material

2021-10-02 14:08:38.413758
Old Total Allocation: 550000.00: New Total Allocation: 820100 : Task: 10559 : Description: Internal Walls - 100 mm thick block walls in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centres)- Sixth Floor-Material

2021-10-02 14:08:38.468024
Old Total Allocation: 595000.00: New Total Allocation: 596840 : Task: 10563 : Description: Internal Walls - 100 mm thick block walls in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centres)- Seventh Floor-Material

2021-10-02 14:08:38.517362
Old Total Allocation: 585000.00: New Total Allocation: 716845 : Task: 10565 : Description: Internal Walls - 100 mm thick block walls in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centres)- Eighth Floor-Material

2021-10-02 14:08:38.551553
Old Total Allocation: 693099.93: New Total Allocation: 713999 : Task: 10567 : Description: Internal Walls - 100 mm thick block walls in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centres)- Ninth Floor-Material

2021-10-02 14:08:38.630880
Old Total Allocation: 10479.00: New Total Allocation: 81179 : Task: 10573 : Description:  Internal Walls - 100 mm thick block walls in cement and sand 1:5 mix including providing concrete stiffeners (at suitable centres)- Twelth Floor-Material

2021-10-02 14:08:40.166039
Old Total Allocation: 200772.18: New Total Allocation: 39075 : Task: 10692 : Description:  Grade 35 Reinforced Cement Concrete -lift Pit Base-Material

2021-10-02 14:08:40.265835
Old Total Allocation: 8400.00: New Total Allocation: 90000 : Task: 10700 : Description: Grade 35 Reinforced Cement Concrete -Ground Floor Slab-Machinery

2021-10-02 14:08:40.356264
Old Total Allocation: 202575.00: New Total Allocation: 98325 : Task: 10707 : Description: Grade 25 Reinforced Cement Concrete -Core wall - lift &amp; staircase-Material

2021-10-02 14:08:40.397926
Old Total Allocation: 27751.89: New Total Allocation: 294 : Task: 10710 : Description: Grade 25 Reinforced Cement Concrete -Beams-Material

2021-10-02 14:08:40.545830
Old Total Allocation: 143298.27: New Total Allocation: 50900 : Task: 10722 : Description: Grade 25 Reinforced Cement Concrete -Steps and waist in staircase-Material

2021-10-02 14:08:40.653280
Old Total Allocation: 32485.46: New Total Allocation: 32235 : Task: 10730 : Description: Grade 25 Reinforced Cement Concrete (FF to SF) -lift &amp; staircase-Machinery

2021-10-02 14:08:40.674300
Old Total Allocation: 407700.00: New Total Allocation: 443550 : Task: 10731 : Description: Grade 25 Reinforced Cement Concrete (FF to SF) -lift &amp; staircase-Material

2021-10-02 14:08:40.753332
Old Total Allocation: 7954.78: New Total Allocation: 69 : Task: 10737 : Description: Grade 25 Reinforced Cement Concrete (FF to SF) -Ramp - from 1st floor to 2nd Floor-Material

2021-10-02 14:08:40.831458
Old Total Allocation: 1377775.92: New Total Allocation: 1283250 : Task: 10743 : Description: Grade 25 Reinforced Cement Concrete (FF to SF) -Suspended slab-Material

2021-10-02 14:08:42.577530
Old Total Allocation: 6126.45: New Total Allocation: 6126.45 : Task: 10881 : Description: Other Fixing Accessories-Material

2021-10-02 14:08:42.673260
Old Total Allocation: 6006.74: New Total Allocation: 6006.74 : Task: 10888 : Description: GI Tape-Material

2021-10-02 14:08:43.432635
Old Total Allocation: 27570.00: New Total Allocation: 83070 : Task: 10950 : Description: Provide &amp; Maintaining Office Facilities ,Staff Facilities, Temperay storers, Meting rooms

2021-10-02 14:08:43.547732
Old Total Allocation: 163480.46: New Total Allocation: 290360 : Task: 10959 : Description: Concrete work

2021-10-02 14:08:43.590895
Old Total Allocation: 7725.00: New Total Allocation: 30000 : Task: 10962 : Description: Grade 25 Reinforced Cement Concrete (FF to SF) -Concrete guard wall at 1st floor-Machinery

2021-10-02 14:08:43.707827
Old Total Allocation: 0.00: New Total Allocation: 17100 : Task: 10968 : Description: Grade 25 Reinforced Cement Concrete (SF to TF) Beams-Machinery

2021-10-02 14:08:43.726124
Old Total Allocation: 403094.44: New Total Allocation: 402950 : Task: 10969 : Description: Grade 25 Reinforced Cement Concrete (SF to TF) Suspended slab-Material

2021-10-02 14:08:43.756073
Old Total Allocation: 137300.00: New Total Allocation: 172300 : Task: 10971 : Description: Grade 25 Reinforced Cement Concrete (SF to TF) Suspended slab-Machinery

2021-10-02 14:08:44.22060
Old Total Allocation: 77855.56: New Total Allocation: 850 : Task: 10993 : Description: Grade 25 Reinforced Cement Concrete (TF to FF) Steps and waist in staircase-Material

2021-10-02 14:08:44.152111
Old Total Allocation: 1766875.26: New Total Allocation: 1814150 : Task: 10999 : Description: Grade 25 Reinforced Cement Concrete (Typical Floors) Columns-Material

2021-10-02 14:08:44.203211
Old Total Allocation: 994745.80: New Total Allocation: 1033650 : Task: 11002 : Description: Grade 25 Reinforced Cement Concrete (Typical Floors) Core wall - lift &amp; staircase-Material

2021-10-02 14:08:44.248252
Old Total Allocation: 329230.23: New Total Allocation: 337300 : Task: 11005 : Description: Grade 25 Reinforced Cement Concrete (Typical Floors) Beams-Material

2021-10-02 14:08:44.292173
Old Total Allocation: 2974748.04: New Total Allocation: 2782900 : Task: 11008 : Description: Grade 25 Reinforced Cement Concrete (Typical Floors) Suspended slab-Material

2021-10-02 14:08:44.359426
Old Total Allocation: 37788.93: New Total Allocation: 38300 : Task: 11013 : Description: Grade 25 Reinforced Cement Concrete (Typical Floors) Steps and waist in staircase-Machinery

2021-10-02 14:08:44.377422
Old Total Allocation: 368075.56: New Total Allocation: 130175 : Task: 11014 : Description: Grade 25 Reinforced Cement Concrete (Typical Floors)150mm thick landing slabs.-Material

2021-10-02 14:08:44.529084
Old Total Allocation: 116698.00: New Total Allocation: 1102.5 : Task: 11026 : Description: Grade 25 Reinforced Cement Concrete -columns-Material

2021-10-02 14:08:44.575610
Old Total Allocation: 454999.08: New Total Allocation: 477000 : Task: 11029 : Description:  Grade 25 Reinforced Cement Concrete -Core wall - lift &amp; staircase-Material

2021-10-02 14:08:44.605236
Old Total Allocation: 30000.00: New Total Allocation: 36300 : Task: 11031 : Description:  Grade 25 Reinforced Cement Concrete -Core wall - lift &amp; staircase-Machinery

2021-10-02 14:08:44.713274
Old Total Allocation: 466258.01: New Total Allocation: 4500 : Task: 11039 : Description: Grade 25 Reinforced Cement Concrete -Guard wall at roof top-Labour

2021-10-02 14:08:44.849007
Old Total Allocation: 50450.00: New Total Allocation: 95000 : Task: 11049 : Description: Grade 25 Reinforced Cement Concrete - Allow for water tank covering, SS ladders &amp; openings-Machinery

2021-10-02 14:08:44.866657
Old Total Allocation: 223348.32: New Total Allocation: 213300 : Task: 11050 : Description: Formworking for Sides of Pile caps including anchorage-Material

2021-10-02 14:08:44.945852
Old Total Allocation: 104193.20: New Total Allocation: 99500 : Task: 11056 : Description: Formworking for  Sides of Ground floor beams in the Above 300mm wide-Material

2021-10-02 14:08:45.22376
Old Total Allocation: 59524.23: New Total Allocation: 54600 : Task: 11062 : Description:  Formworking for Sides of Ground floor beams in the Bottom of Water sump cover slab - suspended-Material

2021-10-02 14:08:45.168024
Old Total Allocation: 18800.00: New Total Allocation: 14300 : Task: 11072 : Description: Formworking for Sides of Ground floor Columns -Above 300mm wide-Material

2021-10-02 14:08:45.210099
Old Total Allocation: 48851.79: New Total Allocation: 45100 : Task: 11074 : Description: Formworking for Sides of Ground floor Columns -Sides of Core wall - lift &amp; staircase-Material

2021-10-02 14:08:45.321827
Old Total Allocation: 634925.12: New Total Allocation: 582400 : Task: 11082 : Description: Formworking for Sides of Ground floor Suspended slab -Bottom of slabs-Material

2021-10-02 14:08:45.545237
Old Total Allocation: 187076.15: New Total Allocation: 171600 : Task: 11100 : Description: Formworking for Sides of First floor/Sides of Columns -Sides of Core wall - lift &amp; staircase-Material

2021-10-02 14:08:45.575703
Old Total Allocation: 32429.98: New Total Allocation: 15300 : Task: 11102 : Description: Formworking for Sides of First floor/Beams -225mm wide - bottoms-Material

2021-10-02 14:08:45.681178
Old Total Allocation: 313515.63: New Total Allocation: 296400 : Task: 11108 : Description: FFormworking for Sides of First floor/Suspended Slab Bottom of slabs-Material

2021-10-02 14:08:46.5996
Old Total Allocation: 66875.00: New Total Allocation: 66000 : Task: 11132 : Description: Formworking for Second Floor Beams -Above 300mm wide - sides-Material

2021-10-02 14:08:46.88129
Old Total Allocation: 567987.08: New Total Allocation: 258000.42 : Task: 11138 : Description: Formworking for Second Floor Suspended Slab -Bottom of slabs-Material

2021-10-02 14:08:46.197878
Old Total Allocation: 9364.84: New Total Allocation: 8400 : Task: 11144 : Description: Formworking for Second Floor Suspended Slab -Bottom of staircase landing slabs.-Material

2021-10-02 14:08:46.264284
Old Total Allocation: 2400.45: New Total Allocation: 2100 : Task: 11148 : Description: Formworking for Second Floor Suspended Slab -Edge of openings in lift with not exceeding 300mm	-Material

2021-10-02 14:08:46.429509
Old Total Allocation: 7000.00: New Total Allocation: 5000 : Task: 11160 : Description: Formworking for Third Floor Suspended slab -Bottom of slabs-Material

2021-10-02 14:08:46.449056
Old Total Allocation: 348000.00: New Total Allocation: 280000 : Task: 11161 : Description: Formworking for Third Floor Suspended slab -Bottom of slabs-Labour

2021-10-02 14:08:46.537544
Old Total Allocation: 12500.00: New Total Allocation: 4500 : Task: 11166 : Description: Formworking for Third Floor Suspended slab -&#039;Bottom of staircase landing slabs.	-Material

2021-10-02 14:08:46.594129
Old Total Allocation: 101032.87: New Total Allocation: 114615.24 : Task: 11170 : Description: Formworking for Typical Floors/Sides of Columns -Above 300mm wide-Material

2021-10-02 14:08:46.629511
Old Total Allocation: 663022.30: New Total Allocation: 668926.83 : Task: 11172 : Description: Formworking for Typical Floors/ Sides of Core wall - lift &amp; staircase-Material

2021-10-02 14:08:46.725889
Old Total Allocation: 240055.64: New Total Allocation: 262500 : Task: 11176 : Description: Formworking for Typical Floors/Sides Beams - Above 300mm wide - sides-Material

2021-10-02 14:08:46.762758
Old Total Allocation: 443075.24: New Total Allocation: 455000 : Task: 11178 : Description: Formworking for Typical Floors/Suspended slab - Side boards - 150mm wide-Material

2021-10-02 14:08:46.794691
Old Total Allocation: 1853838.32: New Total Allocation: 1342680 : Task: 11180 : Description: Formworking for Typical Floors/Suspended slab - Bottom of slabs-Material

2021-10-02 14:08:46.815169
Old Total Allocation: 1390942.15: New Total Allocation: 1116500 : Task: 11181 : Description: Formworking for Typical Floors/Suspended slab - Bottom of slabs-Labour

2021-10-02 14:08:46.858357
Old Total Allocation: 133466.35: New Total Allocation: 126900 : Task: 11184 : Description: Formworking for Typical Floors/Suspended slab - Risers and sides of waist in staircases - 150mm high-Material

2021-10-02 14:08:47.176007
Old Total Allocation: 52064.19: New Total Allocation: 8000 : Task: 11206 : Description: Formworking For Bottom of Lift machine room roof slab &amp; water tank slab-Material

2021-10-02 14:08:47.218951
Old Total Allocation: 4923715.65: New Total Allocation: 7743839 : Task: 11208 : Description: Reinforcement in insitu concrete- Pile caps including anchorage-Material

2021-10-02 14:08:47.276618
Old Total Allocation: 343228.25: New Total Allocation: 2488600 : Task: 11212 : Description: Reinforcement in insitu concrete-Water sump base-Material

2021-10-02 14:08:47.308552
Old Total Allocation: 323522.01: New Total Allocation: 20800 : Task: 11214 : Description: Reinforcement in insitu concrete- Water sump wall	-Material

2021-10-02 14:08:47.340520
Old Total Allocation: 0.00: New Total Allocation: 64000 : Task: 11216 : Description: Reinforcement in insitu concrete- Water sump cover slab - suspended	-Material

2021-10-02 14:08:47.373575
Old Total Allocation: 217947.72: New Total Allocation: 168950 : Task: 11218 : Description: Reinforcement in insitu concrete- Water sump beams-Material

2021-10-02 14:08:47.405906
Old Total Allocation: 25258.01: New Total Allocation: 20750 : Task: 11220 : Description: Reinforcement in insitu concrete- Lift pit base-Material

2021-10-02 14:08:47.438822
Old Total Allocation: 15000.00: New Total Allocation: 53400 : Task: 11222 : Description: Reinforcement in insitu concrete- lift pit walls-Material

2021-10-02 14:08:47.473006
Old Total Allocation: 410000.00: New Total Allocation: 2276400 : Task: 11224 : Description: Reinforcement in insitu concrete- Ground Floor Slab	-Material

2021-10-02 14:08:47.504087
Old Total Allocation: 1260889.60: New Total Allocation: 25600 : Task: 11226 : Description: Reinforcement in insitu concrete (GF-FF)- Grade 25 Reinforced Cement Concrete -Columns-Material

2021-10-02 14:08:47.560702
Old Total Allocation: 274496.00: New Total Allocation: 924496 : Task: 11230 : Description: Reinforcement in insitu concrete (GF-FF) -Grade 25 Reinforced Cement Concrete -Beams-Material

2021-10-02 14:08:47.621700
Old Total Allocation: 0.00: New Total Allocation: 448000 : Task: 11234 : Description: Reinforcement in insitu concrete (GF-FF)- Grade 25 Reinforced Cement Concrete -Ramp - from ground to 1st Floor-Material

2021-10-02 14:08:47.673115
Old Total Allocation: 100000.00: New Total Allocation: 612000 : Task: 11236 : Description: Reinforcement in insitu concrete (GF-FF)- Grade 25 Reinforced Cement Concrete -Ramp beams-Material

2021-10-02 14:08:47.792170
Old Total Allocation: 214016.00: New Total Allocation: 1558016 : Task: 11244 : Description: Reinforcement in insitu concrete (FF-SF)- Grade 25 Reinforced Cement Concrete (FF to SF) -lift &amp; staircase-Material

2021-10-02 14:08:47.838230
Old Total Allocation: 143228.63: New Total Allocation: 143930 : Task: 11245 : Description: Reinforcement in insitu concrete (FF-SF)- Grade 25 Reinforced Cement Concrete (FF to SF) -lift &amp; staircase-Labour

2021-10-02 14:08:47.858475
Old Total Allocation: 100000.00: New Total Allocation: 1661600 : Task: 11246 : Description: Reinforcement in insitu concrete (FF-SF)- Grade 25 Reinforced Cement Concrete (FF to SF) -Beams	-Material

2021-10-02 14:08:47.917364
Old Total Allocation: 100000.00: New Total Allocation: 407200 : Task: 11250 : Description: Reinforcement in insitu concrete (FF-SF)- Ramp beams-Material

2021-10-02 14:08:47.947436
Old Total Allocation: 3604208.00: New Total Allocation: 4254208 : Task: 11252 : Description: Reinforcement in insitu concrete (FF-SF)- Grade 25 Reinforced Cement Concrete (FF to SF) -Suspended slab-Material

2021-10-02 14:08:47.978708
Old Total Allocation: 100231.14: New Total Allocation: 181800 : Task: 11254 : Description: Reinforcement in insitu concrete (FF-SF)- Grade 25 Reinforced Cement Concrete (FF to SF) -Steps and waist in staircase-Material

2021-10-02 14:08:48.9063
Old Total Allocation: 44000.00: New Total Allocation: 83000 : Task: 11256 : Description: Reinforcement in insitu concrete (FF-SF)- Grade 25 Reinforced Cement Concrete (FF to SF) -150mm thick landing slabs.-Material

2021-10-02 14:08:48.63300
Old Total Allocation: 454907.75: New Total Allocation: 3279645.25 : Task: 11260 : Description: Reinforcement in insitu concrete (SF-TF)- Grade 25 Reinforced Cement Concrete (FF to SF) -Columns-Material

2021-10-02 14:08:48.124192
Old Total Allocation: 290000.00: New Total Allocation: 1518800 : Task: 11262 : Description: Reinforcement in insitu concrete (SF-TF)- Grade 25 Reinforced Cement Concrete (FF to SF) -lift &amp; staircase-Material

2021-10-02 14:08:48.172390
Old Total Allocation: 996.15: New Total Allocation: 330120 : Task: 11264 : Description: Reinforcement in insitu concrete (SF-TF)- Grade 25 Reinforced Cement Concrete (FF to SF) -Beams	-Material

2021-10-02 14:08:48.211664
Old Total Allocation: 2030000.00: New Total Allocation: 2964400 : Task: 11266 : Description: Reinforcement in insitu concrete (SF-TF)- Grade 25 Reinforced Cement Concrete (FF to SF) -Suspended slab-Material

2021-10-02 14:08:48.244080
Old Total Allocation: 51701.10: New Total Allocation: 52200 : Task: 11268 : Description: Reinforcement in insitu concrete (SF-TF)- Grade 25 Reinforced Cement Concrete (FF to SF) -Steps and waist in staircase-Material

2021-10-02 14:08:48.272597
Old Total Allocation: 51616.33: New Total Allocation: 60600 : Task: 11270 : Description: Reinforcement in insitu concrete (SF-TF)- Grade 25 Reinforced Cement Concrete (FF to SF) -150mm thick landing slabs.-Material

2021-10-02 14:08:48.302680
Old Total Allocation: 25000.00: New Total Allocation: 50600 : Task: 11272 : Description: Reinforcement in insitu concrete (SF-TF)- Concrete guard wall at 1st floor-Material

2021-10-02 14:08:48.331983
Old Total Allocation: 0.00: New Total Allocation: 832000 : Task: 11274 : Description: Reinforcement in insitu concrete (TF-FF)- Columns	-Material

2021-10-02 14:08:48.385735
Old Total Allocation: 118102.50: New Total Allocation: 2817102.5 : Task: 11278 : Description: Reinforcement in insitu concrete (TF-FF)-Beams-Material

2021-10-02 14:08:48.417483
Old Total Allocation: 153730.00: New Total Allocation: 2745730 : Task: 11280 : Description: Reinforcement in insitu concrete (TF-FF)-Suspended slab-Material

2021-10-02 14:08:48.448409
Old Total Allocation: 83195.37: New Total Allocation: 82500 : Task: 11282 : Description: Reinforcement in insitu concrete (TF-FF)-Steps and waist in staircase-Material

2021-10-02 14:08:48.501845
Old Total Allocation: 1895711.11: New Total Allocation: 4163500 : Task: 11286 : Description: Reinforcement in insitu concrete (Typical)- Grade 25 Reinforced Cement Concrete (Typical Floors) Columns	-Material

2021-10-02 14:08:48.530641
Old Total Allocation: 731500.00: New Total Allocation: 1464000 : Task: 11288 : Description: Reinforcement in insitu concrete (Typical)- Grade 25 Reinforced Cement Concrete (Typical Floors) Core wall - lift &amp; staircase-Material

2021-10-02 14:08:48.585790
Old Total Allocation: 1132500.00: New Total Allocation: 3450000 : Task: 11292 : Description: Reinforcement in insitu concrete (Typical)- Grade 25 Reinforced Cement Concrete (Typical Floors) Suspended slab-Material

2021-10-02 14:08:48.616244
Old Total Allocation: 265770.95: New Total Allocation: 313215.58 : Task: 11294 : Description: Reinforcement in insitu concrete (Typical)- Grade 25 Reinforced Cement Concrete (Typical Floors) Steps and waist in staircase	-Material

2021-10-02 14:08:48.729021
Old Total Allocation: 0.00: New Total Allocation: 520000 : Task: 11300 : Description: Reinforcement in insitu concrete -Grade 25 Reinforced Cement Concrete - Other concrete walls-Material

2021-10-02 14:08:48.809486
Old Total Allocation: 100000.00: New Total Allocation: 1300000 : Task: 11306 : Description: Reinforcement in insitu concrete -Grade 25 Reinforced Cement Concrete -Core wall - lift &amp; staircase-Material

2021-10-02 14:08:48.866089
Old Total Allocation: 197717.57: New Total Allocation: 199000 : Task: 11310 : Description: Reinforcement in insitu concrete -Grade 25 Reinforced Cement Concrete -Water tank slab beams-Material

2021-10-02 14:08:48.898085
Old Total Allocation: 50000.00: New Total Allocation: 110000 : Task: 11312 : Description: Reinforcement in insitu concrete - Guard wall at roof top-Material

2021-10-02 14:08:49.312638
Old Total Allocation: 200000.00: New Total Allocation: 212000 : Task: 11342 : Description: Random rubble masonry in foundation in 1:5 cement &amp; sand moter.-Material

2021-10-02 14:08:51.63661
Old Total Allocation: 18648.43: New Total Allocation: 16850 : Task: 11462 : Description: 16mm thick external plaster in cement and sand 1:3 finished semi rough to the walls -Ground Floor-Material

2021-10-02 14:08:51.318183
Old Total Allocation: 55500.00: New Total Allocation: 51500 : Task: 11482 : Description:  16mm thick external plaster in cement and sand 1:3 finished semi rough to the walls -Tenth Floor-Material

2021-10-02 14:08:51.348904
Old Total Allocation: 42700.00: New Total Allocation: 42000 : Task: 11484 : Description: 16mm thick external plaster in cement and sand 1:3 finished semi rough to the walls -Eleventh Floor-Material

2021-10-02 14:08:51.576650
------------------Script Completed----------------------------

2021-10-02 15:47:59.722854
==================Script Sarted==========================

2021-10-02 15:47:59.960538
10000 records selected

2021-10-02 15:48:00.386148
Old Total Allocation: 4908.06: New Total Allocation: 100 : Task: 11512 : Description: Gas Pipe Distribution

2021-10-02 15:48:03.548959
Negative allocation found: -70378.00 : Task: 11662 : Description: Alluminium Tape-Material

2021-10-02 15:48:04.430702
Old Total Allocation: 408309.71: New Total Allocation: 412575.71 : Task: 11728 : Description: Main Items

2021-10-02 15:48:05.440282
Old Total Allocation: 0.00: New Total Allocation: 38500 : Task: 11808 : Description: Concrete invert channel: Construct minimum 150mm thick new RC channel fully embedded into the base slab by anchors-Material

2021-10-02 15:48:05.491678
Old Total Allocation: 0.00: New Total Allocation: 955000 : Task: 11810 : Description: Coating:CH.0+763m to CH.0+789m : Minimum 50mm shotcrete with steel reinforced mesh on to the existing unlined brick masonry arch roof-Sub Contract Payment

2021-10-02 15:48:06.710044
Old Total Allocation: 0.00: New Total Allocation: 329500 : Task: 11857 : Description: Rehabilitation : CH.0+197m to CH.0+257m : Concrete invert channel-Material

2021-10-02 15:48:08.242986
Old Total Allocation: 620000.00: New Total Allocation: 777500 : Task: 11973 : Description: Pre Rehabilitation Repairs:CH.0+202m to CH.0+277m:Concrete invert channel-Material

2021-10-02 15:48:08.709911
Negative allocation found: -486400.00 : Task: 12010 : Description: Cable

2021-10-02 15:48:08.738710
Old Total Allocation: 2077851.70: New Total Allocation: 2077851.7 : Task: 12012 : Description: Pipes and Fittings -Material

2021-10-02 15:48:09.258125
Negative allocation found: -59500.00 : Task: 12046 : Description: Earth Pit-Material

2021-10-02 15:48:09.947989
Old Total Allocation: 305.06: New Total Allocation: 305.07 : Task: 12099 : Description: Power Cable-Material

2021-10-02 15:48:12.344556
Old Total Allocation: 103901.95: New Total Allocation: 103901.95 : Task: 12274 : Description: Copper Tape-Material

2021-10-02 15:48:14.672945
Old Total Allocation: 1197378.19: New Total Allocation: 1247383 : Task: 12404 : Description: Sub-Contractor Charges -Sub Contract Payment

2021-10-02 15:48:14.833653
Old Total Allocation: 116500.00: New Total Allocation: 120750 : Task: 12417 : Description: Allow for Environmental Management as specified in EMP-Machinery

2021-10-02 15:48:14.879863
Old Total Allocation: 1383566.64: New Total Allocation: 1977209 : Task: 12419 : Description: Provide and maintain temporary Office for engineers -Preliminary

2021-10-02 15:48:14.989006
Old Total Allocation: 514400.00: New Total Allocation: 518500 : Task: 12426 : Description: Allow for providing Assistance to Engineers-Preliminary

2021-10-02 15:48:15.116233
Old Total Allocation: 71300.00: New Total Allocation: 267425 : Task: 12428 : Description: Allow for Environmental Management as specified in EMP-Labour

2021-10-02 15:48:15.673588
Old Total Allocation: 49200.00: New Total Allocation: 84860 : Task: 12457 : Description: Provision of Pipe Work - Sluice valve - 80mm Dia.-Material

2021-10-02 15:48:15.900286
Old Total Allocation: 30000.00: New Total Allocation: 86332.5 : Task: 12467 : Description: Provision of Pipe Work - DI Pipe Piece -  80mm Dia. &amp; 1200mm Long Single Flange DI pipe pieces with Puddle Collar-Material

2021-10-02 15:48:16.12930
Old Total Allocation: 70150.00: New Total Allocation: 121025 : Task: 12469 : Description: Provision of Pipe Work - DI Pipe Piece - 80mm Dia. &amp; 1200mm Long Plain ended DI pipe pieces-Material

2021-10-02 15:48:16.160332
Old Total Allocation: 60600.00: New Total Allocation: 65750 : Task: 12471 : Description: Provision of Pipe Work - Surface Box - Heavy Duty DI surface box size of 150x150x100mm clear opening at centre-Material

2021-10-02 15:48:16.234247
Old Total Allocation: 58000.00: New Total Allocation: 116125 : Task: 12473 : Description: Provision of Pipe Work -- Section Valve - Sluice Valve -  80mm Dia. Sluice Valve-Material

2021-10-02 15:48:16.436322
Old Total Allocation: 96000.00: New Total Allocation: 117000 : Task: 12474 : Description: Provision of Pipe Work -- Section Valve - Sluice Valve - 100mm Dia. Sluice Valve-Material

2021-10-02 15:48:16.456416
Old Total Allocation: 0.00: New Total Allocation: 36000 : Task: 12475 : Description: Provision of Pipe Work -- Section Valve -  DI Pipe Pieces -  80mm Dia. &amp; 1200mm Long, DI Single Flange pipe Pieces with Puddle Collar-Material

2021-10-02 15:48:16.477007
Old Total Allocation: 63500.00: New Total Allocation: 69000 : Task: 12476 : Description: Provision of Pipe Work -- Section Valve -  DI Pipe Pieces -  100mm Dia. &amp; 1200mm Long, DI Single Flange pipe Pieces with Puddle Collar-Material

2021-10-02 15:48:16.496160
Old Total Allocation: 91500.00: New Total Allocation: 179684 : Task: 12477 : Description: Provision of Pipe Work -- Section Valve -  DI Pipe Pieces -  80mm Dia. &amp; 1200mm Long, DI Double Flange pipe Pieces with puddle collar-Material

2021-10-02 15:48:16.541308
Old Total Allocation: 36000.00: New Total Allocation: 54000 : Task: 12480 : Description: 100mm Dia. DI Flange Adaptor-Material

2021-10-02 15:48:16.687479
Old Total Allocation: 0.00: New Total Allocation: 110400 : Task: 12491 : Description: 80mm Dia. &amp; 2000mm long DI Double Flange pipe Pieces  for Culvert Crossings Type E-Material

2021-10-02 15:48:16.744934
Old Total Allocation: 1400.00: New Total Allocation: 29900 : Task: 12493 : Description: DI Flange Tee for Airvalve Connection 80 x 25mm Dia.-Material

2021-10-02 15:48:16.881735
Old Total Allocation: 30000.00: New Total Allocation: 277000 : Task: 12495 : Description: Supply Blue Coloured Polyethylene Marker Tapes 150 mm Wide with words-Material

2021-10-02 15:48:17.236505
Old Total Allocation: 605703.00: New Total Allocation: 695703 : Task: 12498 : Description: Washout Valve Chamber (80mm Dia. DI suit to 63mm Dia. PVC Pipe line)-Material

2021-10-02 15:48:17.268928
Old Total Allocation: 686500.00: New Total Allocation: 712920 : Task: 12499 : Description: Washout Valve Chamber (80mm Dia. DI suit to 90mm Dia. PVC Pipe line)-Material

2021-10-02 15:48:17.304814
Old Total Allocation: 382800.00: New Total Allocation: 591050 : Task: 12501 : Description: Section Valve Chamber (80mm Dia. DI suit to 63mm Dia. PVC Pipe line)-Material

2021-10-02 15:48:17.333598
Old Total Allocation: 648500.00: New Total Allocation: 814174.25 : Task: 12502 : Description: Section Valve Chamber (80mm Dia. DI suit to 90mm Dia. PVC Pipe line)-Material

2021-10-02 15:48:17.373548
Old Total Allocation: 16500.00: New Total Allocation: 98050 : Task: 12504 : Description: Culvert Crossing Type E (80mm Dia. DI suit to 90mm Dia. PVC Pipe line)-Material

2021-10-02 15:48:17.727224
Old Total Allocation: 0.00: New Total Allocation: 22500 : Task: 12526 : Description: Section Valve Chamber (80mm Dia. DI suit to 90mm Dia. PVC Pipe line)-Machinery

2021-10-02 15:48:18.27021
Old Total Allocation: 183500.00: New Total Allocation: 190495 : Task: 12543 : Description: Laying Of PNT 7 (Type 600) PVC 63mm Dia. Pipes (Rubber Ring Joints) -Sub Contract Payment

2021-10-02 15:48:18.425978
Old Total Allocation: 412560.00: New Total Allocation: 762582.5 : Task: 12559 : Description: Single orific Airvalve chamber as shown in Detail Drawing with  DI manhole cover.-Sub Contract Payment

2021-10-02 15:48:18.497729
Old Total Allocation: 130200.00: New Total Allocation: 150575 : Task: 12560 : Description: Washout Valve Chamber (80mm Dia. DI suit to 63mm Dia. PVC Pipe line)-Sub Contract Payment

2021-10-02 15:48:18.544841
Old Total Allocation: 0.00: New Total Allocation: 44550 : Task: 12563 : Description: Fixing of Heavy Duty DI surface box size of 150x150x100mm clear opening at centre as directed by engineer-Sub Contract Payment

2021-10-02 15:48:18.567740
Old Total Allocation: 50000.00: New Total Allocation: 52200 : Task: 12564 : Description: Section Valve Chamber (80mm Dia. DI suit to 63mm Dia. PVC Pipe line)-Sub Contract Payment

2021-10-02 15:48:20.566522
Old Total Allocation: 55150.00: New Total Allocation: 61000 : Task: 12699 : Description: Supply &amp; Fixing 1.8m height  Chain link fence with 50x50mm PVC coated wire mesh (woven in hexagonal shape, gauge 8)  fixed to concrete post at Treatment plant. Rate to be including  concrete base and rubble masonary  as per the  Drawings (Refer Drawing No - WaSSIP/RWS/KILI/IYA/STD/ 13 &amp; 13-1) &amp; Directed by the Engineer-Sub Contract Payment

2021-10-02 15:48:20.817311
Old Total Allocation: 1421850.00: New Total Allocation: 2313906 : Task: 12702 : Description: Supply &amp; Erect of single arm type solar powered led lamp with pole; Compiled IEC/IEEE Standards and regulations.
Rate to be included Integrated Solar Power LED Lamp with Battery Backup, Pole (5m), Concrete footing and all necessary material to be complete. All complete as shown in the Drawing &amp; specifications and directed by the engineer. 
-Sub Contract Payment

2021-10-02 15:48:20.898177
Old Total Allocation: 154500.00: New Total Allocation: 169325 : Task: 12708 : Description: Preperation surface, compacting, supply and coloured paving 220 x 110 x 80mm (40N/mm2) interlocking paving block.-Sub Contract Payment

2021-10-02 15:48:22.895724
Old Total Allocation: 30000.00: New Total Allocation: 60000 : Task: 12859 : Description: Reinforced Concrete -Grade 25 - 200mm Thickness, Grade 25 Reinforced Concrete for Base Slab -Material

2021-10-02 15:48:23.3286
Old Total Allocation: 386765.66: New Total Allocation: 386765.66 : Task: 12866 : Description: Supplying and fixing Two Layers GI woven mesh around the tank-Material

2021-10-02 15:48:23.772680
Old Total Allocation: 86035.00: New Total Allocation: 136635 : Task: 12916 : Description: Reinforcement 16 mm Dia For Base Slab-Material

2021-10-02 15:48:24.863251
Old Total Allocation: 35000.00: New Total Allocation: 40750 : Task: 12979 : Description: Reinforcement - 12mm Dia For wall-Material

2021-10-02 15:48:26.328216
Old Total Allocation: 100000.00: New Total Allocation: 223315 : Task: 13091 : Description: 225mm thick vertical straight, common Block masonry walls in cement and sand mortar 1:5.-Material

2021-10-02 15:48:30.105907
Old Total Allocation: 0.00: New Total Allocation: 2710 : Task: 13256 : Description: Concrete in Floors, 75mm thikness mass concrete-Material

2021-10-02 15:48:32.211844
Old Total Allocation: 0.00: New Total Allocation: 109200 : Task: 13347 : Description: Supply two sets of new 80mm DI PN16 suction pipes (Foot valve to Pump house) &amp; delivery pipes all necessary items for Intake 1 -Sub Contract Payment

2021-10-02 15:48:32.383964
Old Total Allocation: 0.00: New Total Allocation: 176000 : Task: 13348 : Description: Supply two sets of new 80mm DI PN16 suction pipes and delivery all necessary items for Intake 2 -Sub Contract Payment

2021-10-02 15:48:33.48378
Old Total Allocation: 0.00: New Total Allocation: 97216 : Task: 13363 : Description: Supply and delivery suitable rated PVC/SWA/XLPE/CU Power and Earth cable for each Pumps (2 Nos.) from the Pump Control panel in the Pump house.Cable size shall confirm by the contractor.  -Sub Contract Payment

2021-10-02 15:48:33.154956
Old Total Allocation: 0.00: New Total Allocation: 142600 : Task: 13366 : Description: Installation, fixing and laying of equipment, Cables &amp; accessories supplied above items 16.18 to 16.20 of Bill No -16-Sub Contract Payment

2021-10-02 15:48:33.453638
Old Total Allocation: 40000.00: New Total Allocation: 88608 : Task: 13373 : Description: Allow for Installation, testing and commissioning of Incoming Main panels, Pump Controls Panels and Other Panels, equipment &amp; accessories supplied under Bill No 16 -Sub Contract Payment

2021-10-02 15:48:33.622045
Old Total Allocation: 731020.19: New Total Allocation: 731020.19 : Task: 13377 : Description: Point Wiring

2021-10-02 15:48:33.873212
Old Total Allocation: 343840.00: New Total Allocation: 668840 : Task: 13388 : Description: Food,Beverage &amp; Entertainment-General Overhead

2021-10-02 15:48:34.117656
Old Total Allocation: 1688830.00: New Total Allocation: 5109624 : Task: 13394 : Description: Salary &amp; Allowance - Officer-General Overhead

2021-10-02 15:48:37.761744
Old Total Allocation: 471311.13: New Total Allocation: 501520 : Task: 13589 : Description: G. 25 Concrete For Ground Floor Slab  (150 mm thick )-Material

2021-10-02 15:48:39.907718
Old Total Allocation: 14900.00: New Total Allocation: 50300 : Task: 13642 : Description: Steel I Beam 200 X 100 10 kg/ m Spray painted with Matt Balack color-Sub Contract Payment

2021-10-02 15:48:41.685710
Old Total Allocation: 1245.20: New Total Allocation: 1245.2 : Task: 13746 : Description: Other Fixing Accessories-Material

2021-10-02 15:48:41.997299
Negative allocation found: -250.00 : Task: 13762 : Description: Nut and Bolt 19mm x 25mm-Material

2021-10-02 15:48:42.25491
Negative allocation found: -495.00 : Task: 13763 : Description: Nut and Bolt 24mm x 25mm-Material

2021-10-02 15:48:42.42098
Negative allocation found: -100.00 : Task: 13764 : Description: Nut and Bolt 16mm x 20mm-Material

2021-10-02 15:48:42.175906
Negative allocation found: -150.00 : Task: 13765 : Description: Nut and Bolt 10mm x 12mm-Material

2021-10-02 15:48:42.203474
Negative allocation found: -900.00 : Task: 13766 : Description: 8mm (20m x 3) Guy Cable-Material

2021-10-02 15:48:42.225778
Negative allocation found: -120.00 : Task: 13767 : Description: Tumming Buckle-Material

2021-10-02 15:48:42.250809
Negative allocation found: -360.00 : Task: 13768 : Description: Bulldo Clips-Material

2021-10-02 15:48:42.450282
Negative allocation found: -150.00 : Task: 13769 : Description: Thimbal-Material

2021-10-02 15:48:42.518537
Negative allocation found: -1004.00 : Task: 13770 : Description: No 120 Sand Paper-Material

2021-10-02 15:48:42.534528
Negative allocation found: -154.00 : Task: 13771 : Description: No 100 Amari Paper-Material

2021-10-02 15:48:42.565151
Negative allocation found: -743.50 : Task: 13773 : Description: Anti corrosive (White)-Material

2021-10-02 15:48:42.658219
Negative allocation found: -600.00 : Task: 13774 : Description: Thinner-Material

2021-10-02 15:48:42.675871
Negative allocation found: -625.22 : Task: 13775 : Description: Paint Brush 2&quot;-Material

2021-10-02 15:48:42.691812
Negative allocation found: -90.00 : Task: 13776 : Description: L Iron 15mm x 15mm-Material

2021-10-02 15:48:42.708856
Negative allocation found: -360.00 : Task: 13777 : Description: Railing Bar 20mm x 20mm-Material

2021-10-02 15:48:42.952473
Negative allocation found: -5625.00 : Task: 13778 : Description: Refreshment/Entertainment

2021-10-02 15:48:43.107816
Negative allocation found: -4909.00 : Task: 13780 : Description: Site OH / 15%-General Overhead

2021-10-02 15:48:43.458588
Old Total Allocation: 309000.00: New Total Allocation: 408000 : Task: 13805 : Description: Door D4 - Al door(900x2100)

2021-10-02 15:48:43.931406
Old Total Allocation: 52450.00: New Total Allocation: 117450 : Task: 13842 : Description: Floor, wall Finishes : 600x300 glass wall tileGround floor

2021-10-02 15:48:44.33502
Old Total Allocation: 197700.00: New Total Allocation: 193500 : Task: 13843 : Description: Floor, wall Finishes : 600x300 glass wall tile First floor

2021-10-02 15:48:44.52745
Old Total Allocation: 31000.00: New Total Allocation: 271100 : Task: 13844 : Description: Sanitory fittings and accessories - wash basin on vanity

2021-10-02 15:48:44.242167
Old Total Allocation: 300000.00: New Total Allocation: 332400 : Task: 13845 : Description: Sanitory fittings and accessories -Water closet

2021-10-02 15:48:44.263373
Old Total Allocation: 33600.00: New Total Allocation: 70320 : Task: 13846 : Description: Sanitory fittings and accessories -Wall munted wash basin

2021-10-02 15:48:44.448185
Old Total Allocation: 23000.00: New Total Allocation: 41000 : Task: 13847 : Description: Sanitory fittings and accessories -Toilet paper holder

2021-10-02 15:48:44.466536
Old Total Allocation: 0.00: New Total Allocation: 30750 : Task: 13848 : Description: Sanitory fittings and accessories -Urinals

2021-10-02 15:48:45.415877
Old Total Allocation: 35484.26: New Total Allocation: 35484.26 : Task: 13892 : Description: Sum allocated for plumbing work

2021-10-02 15:48:47.199785
Negative allocation found: -14382.42 : Task: 13968 : Description: Earth Cable-Material

2021-10-02 15:48:47.470882
Old Total Allocation: 12358.46: New Total Allocation: 12358.46 : Task: 13975 : Description: Other Fixing Accessories-Material

2021-10-02 15:48:50.182168
Old Total Allocation: 49352.09: New Total Allocation: 49352.09 : Task: 14163 : Description: Travelling and Transport-Labour

2021-10-02 15:48:51.591411
Old Total Allocation: 373959.55: New Total Allocation: 373959.55 : Task: 14274 : Description: Point Wiring

2021-10-02 15:48:51.611191
Old Total Allocation: 19065.91: New Total Allocation: 23367.25 : Task: 14275 : Description: Conduits

2021-10-02 15:48:51.674394
Old Total Allocation: 0.00: New Total Allocation: 2000 : Task: 14279 : Description: Consumables

2021-10-02 15:48:56.553638
Old Total Allocation: 8351494.86: New Total Allocation: 8351494.86 : Task: 14604 : Description: Material-Material

2021-10-02 15:48:57.615423
Old Total Allocation: 3335957.18: New Total Allocation: 3335957.18 : Task: 14678 : Description: Power Cable

2021-10-02 15:48:58.544023
Old Total Allocation: 131348.29: New Total Allocation: 131348.29 : Task: 14750 : Description: Cable

2021-10-02 15:48:59.308858
Old Total Allocation: 244872.33: New Total Allocation: 244872.33 : Task: 14802 : Description: Lightning Protection-Material

2021-10-02 15:49:01.108104
Negative allocation found: -102300.00 : Task: 14938 : Description: DC Clips-Material

2021-10-02 15:49:01.131760
Negative allocation found: -388021.50 : Task: 14939 : Description: Copper Tape-Material

2021-10-02 15:49:01.150246
Negative allocation found: -42500.00 : Task: 14940 : Description: Cross Clamp-Material

2021-10-02 15:49:01.241677
Old Total Allocation: 4615.56: New Total Allocation: 4615.56 : Task: 14947 : Description: Cad Weld Joint for Rod-Material

2021-10-02 15:49:01.311146
Old Total Allocation: 54494.41: New Total Allocation: 54494.41 : Task: 14952 : Description: Other Fixing Accessories-Material

2021-10-02 15:49:01.394590
Old Total Allocation: 25560.84: New Total Allocation: 25560.84 : Task: 14958 : Description: Conduits

2021-10-02 15:49:02.508963
Negative allocation found: -56250.00 : Task: 15028 : Description: AC Cable -Material

2021-10-02 15:49:02.538522
Negative allocation found: -9300.00 : Task: 15030 : Description: DC SPD-Material

2021-10-02 15:49:02.589375
Old Total Allocation: 4670.06: New Total Allocation: 4670.06 : Task: 15034 : Description: Earthing -Material

2021-10-02 15:49:02.609589
Negative allocation found: -11800.00 : Task: 15035 : Description: Veepower Box-Material

2021-10-02 15:49:02.631585
Negative allocation found: -7348.39 : Task: 15036 : Description: Civil cost-Material

2021-10-02 15:49:03.114365
Old Total Allocation: 97375.00: New Total Allocation: 86875 : Task: 15068 : Description: Structure for Front canopy - Design and built suitable steel structure framework to rest front canopy. The cost shall include all required  of  Ms Joint plates, nuts,bolts, J bolts and cleats etc.,  and  Sand blasting to S.A 2.5 &amp; applying two anti-corrosive primer coats and one coat of finish paint of approved colour complete as per drawings, specifications.  

2021-10-02 15:49:03.344355
Old Total Allocation: 994000.00: New Total Allocation: 1020000 : Task: 15083 : Description: Supply and lay 300x600 mm and 25 mm thick granite finish at Reception Lobby with inserts and suitable adhesive as per detail drawings and specifications. (Reception) (Prime cost of tiles Rs.1,200.00 per  sqft.) 

2021-10-02 15:49:03.553369
Old Total Allocation: 1300000.00: New Total Allocation: 1304500 : Task: 15099 : Description: Supply and lay 600x600 mm design carpet tiles , with alumnium jointing strips  thresholds and all necessary to complete work as per detail drawings and specification. (Samples should be approved by the Engineer) (Prime cost sum Rs 225.00 per sq.ft)-Excluding Underlay

2021-10-02 15:49:04.150153
Old Total Allocation: 204850.00: New Total Allocation: 266850 : Task: 15142 : Description: 200 mm thick  solid cement  block wall in SLS approved quality and certified  in cement sand 1:5 mix 

2021-10-02 15:49:04.170873
Old Total Allocation: 50000.00: New Total Allocation: 1240000 : Task: 15143 : Description: Roof top- Open to sky area - Torch applied polymer modified bitumen membrane type, minimum 4mm thick, complete waterproofing system as per manufacture&#039;s specifications and instructions. The Bidder shall refer the roof terrace and parapet details in the Bid document and include all elements as shown in the water proofing system in the open terraces and open to sky slabs. Rate shall include for make floor to adequate slope, bedding layers with chip/mass concrete, protective screed, thermal in

2021-10-02 15:49:04.542657
Old Total Allocation: 24696.82: New Total Allocation: 24000 : Task: 15172 : Description: Cement rendering in cement and sand 1:3 to average 20mm thick finished smooth with suitable adhesive and approved coloured cement floating to the followings.

2021-10-02 15:49:05.633949
Old Total Allocation: 48111.36: New Total Allocation: 48111.37 : Task: 15252 : Description: Extra Work

2021-10-02 15:49:05.666701
Old Total Allocation: 55103.36: New Total Allocation: 53109 : Task: 15254 : Description:  Water Supply pipes and fittings

2021-10-02 15:49:05.732710
Old Total Allocation: 296747.20: New Total Allocation: 296787.2 : Task: 15258 : Description: Plumbing Pipe Fittings &amp; Accessories

2021-10-02 15:49:07.337802
Old Total Allocation: 8185876.67: New Total Allocation: 8185910.67 : Task: 15366 : Description: Cable tray and ladders

2021-10-02 15:49:07.658606
Old Total Allocation: 132630.77: New Total Allocation: 132630.77 : Task: 15387 : Description: Miscellaneous

2021-10-02 15:49:12.754722
Old Total Allocation: 15738.92: New Total Allocation: 15738.92 : Task: 15739 : Description: 2&#039;&#039; GI Pipe-Material

2021-10-02 15:49:12.903653
Old Total Allocation: 73613.94: New Total Allocation: 87053.94 : Task: 15751 : Description: Staff Welfare

2021-10-02 15:49:12.959904
Old Total Allocation: 4662.22: New Total Allocation: 4662.22 : Task: 15755 : Description: Printing & Stationery

2021-10-02 15:49:13.159954
Old Total Allocation: 199130.62: New Total Allocation: 475092.22 : Task: 15771 : Description: Office Maintenance

2021-10-02 15:49:13.178434
Old Total Allocation: 585.69: New Total Allocation: 10485.69 : Task: 15772 : Description: Equipment Maintenance

2021-10-02 15:49:13.472273
Old Total Allocation: 1849337.91: New Total Allocation: 1850032.35 : Task: 15796 : Description: Tendering Expenses

2021-10-02 15:49:13.955084
Old Total Allocation: 84511.68: New Total Allocation: 84511.68 : Task: 15833 : Description: Printing & Stationery

2021-10-02 15:49:14.812970
Old Total Allocation: 46669.51: New Total Allocation: 58466.7 : Task: 15891 : Description: Printing &amp; Stationery

2021-10-02 15:49:14.886943
Old Total Allocation: 60515.01: New Total Allocation: 60515.01 : Task: 15896 : Description: Material

2021-10-02 15:49:14.933029
Old Total Allocation: 326609.98: New Total Allocation: 235797 : Task: 15899 : Description: Material

2021-10-02 15:49:15.53272
Old Total Allocation: 1933.24: New Total Allocation: 1933.24 : Task: 15908 : Description: Printing & Stationery

2021-10-02 15:49:15.72325
Negative allocation found: -91378.00 : Task: 15909 : Description: Travelling/Transport

2021-10-02 15:49:15.100793
Old Total Allocation: 47865.05: New Total Allocation: 47865.05 : Task: 15911 : Description: Equipment Maintenance

2021-10-02 15:49:15.286431
Old Total Allocation: 41532.66: New Total Allocation: 41532.66 : Task: 15925 : Description: Miscellaneous

2021-10-02 15:49:15.947458
Old Total Allocation: 26135.04: New Total Allocation: 26135.04 : Task: 15976 : Description: Sample Expenses

2021-10-02 15:49:16.85231
Old Total Allocation: 448887.22: New Total Allocation: 448887.22 : Task: 15987 : Description: Stock Control

2021-10-02 15:49:17.217308
Old Total Allocation: 3579350.60: New Total Allocation: 11758950.6 : Task: 16061 : Description: Material

2021-10-02 15:49:17.723467
Old Total Allocation: 26366.15: New Total Allocation: 26366.15 : Task: 16101 : Description: Printing & Stationery

2021-10-02 15:49:20.712283
Old Total Allocation: 511099.60: New Total Allocation: 574099.6 : Task: 16320 : Description: Aluminium framed maraine plywood spray painted doo

2021-10-02 15:49:20.755072
Old Total Allocation: 649150.00: New Total Allocation: 700610 : Task: 16323 : Description: Wall Finishes

2021-10-02 15:49:22.434977
Old Total Allocation: 908359.12: New Total Allocation: 938800 : Task: 16460 : Description: Water Tank Area

2021-10-02 15:49:22.831241
Old Total Allocation: 165411.34: New Total Allocation: 165411.34 : Task: 16491 : Description: Point Wiring

2021-10-02 15:49:23.142089
Old Total Allocation: 0.00: New Total Allocation: 2 : Task: 16513 : Description: Fire Pump 2 x 30L/min 25m head

2021-10-02 15:49:23.187367
Old Total Allocation: 53790.00: New Total Allocation: 53793 : Task: 16516 : Description: fire hose cabinet (600mm x 600mm x 400mm)

2021-10-02 15:49:23.206004
Old Total Allocation: 0.00: New Total Allocation: 11 : Task: 16517 : Description: Co2,3kg extinguisher

2021-10-02 15:49:23.224239
Old Total Allocation: 0.00: New Total Allocation: 11 : Task: 16518 : Description: Water 9L Extinguisher

2021-10-02 15:49:23.241389
Old Total Allocation: 0.00: New Total Allocation: 1 : Task: 16519 : Description: Fire Alarm control panel 4zone conventional

2021-10-02 15:49:23.259333
Old Total Allocation: 0.00: New Total Allocation: 6 : Task: 16520 : Description: Manual call point

2021-10-02 15:49:23.276574
Old Total Allocation: 0.00: New Total Allocation: 6 : Task: 16521 : Description: Sounder

2021-10-02 15:49:23.418469
Old Total Allocation: 0.00: New Total Allocation: 8 : Task: 16532 : Description: Fire exit-sign

2021-10-02 15:49:23.545645
Old Total Allocation: 0.00: New Total Allocation: 1 : Task: 16540 : Description: pressure gauge (0-8bar)

2021-10-02 15:49:23.588007
Old Total Allocation: 0.00: New Total Allocation: 1 : Task: 16543 : Description: 25mm dia brass Air relief valve

2021-10-02 15:49:23.605803
Old Total Allocation: 43674.04: New Total Allocation: 40022 : Task: 16544 : Description: pipe Fittings and accessories 

2021-10-02 15:49:24.787411
Old Total Allocation: 2872471.69: New Total Allocation: 3837434 : Task: 16630 : Description: Supply of Pipe Materials , Fittings and Valves-Material

2021-10-02 15:49:25.771470
Old Total Allocation: 170801.40: New Total Allocation: 96420.4 : Task: 16710 : Description: Sch 40 , 15mm dia pipe

2021-10-02 15:49:25.804247
Old Total Allocation: 755.80: New Total Allocation: 768.8 : Task: 16712 : Description: Sch40  , 32mm dia pipe

2021-10-02 15:49:25.835391
Old Total Allocation: 6250.00: New Total Allocation: 9560 : Task: 16713 : Description: 15mm dia bronze gate valve

2021-10-02 15:49:25.928172
Old Total Allocation: 0.00: New Total Allocation: 9 : Task: 16718 : Description: 1m long flexible connection, gas ferrules, hose cl

2021-10-02 15:49:25.956639
Old Total Allocation: 59420.00: New Total Allocation: 59468 : Task: 16719 : Description: Gas controller switch and cable

2021-10-02 15:49:26.69790
Old Total Allocation: 0.00: New Total Allocation: 18900 : Task: 16728 : Description: 1 1/4 inch Ball valve

2021-10-02 15:49:26.110593
Old Total Allocation: 7642.62: New Total Allocation: 3933.74 : Task: 16731 : Description: Other

2021-10-02 15:49:26.134268
Old Total Allocation: 0.00: New Total Allocation: 2300 : Task: 16732 : Description: 20mm dia bronze ball valve

2021-10-02 15:49:26.152167
Old Total Allocation: 0.00: New Total Allocation: 5900 : Task: 16733 : Description: 32mm dia bronze gate valve

2021-10-02 15:49:26.226495
Old Total Allocation: 3993.58: New Total Allocation: 5493.58 : Task: 16739 : Description: Conduits

2021-10-02 15:49:26.465065
Old Total Allocation: 413389.91: New Total Allocation: 442705 : Task: 16756 : Description: Provisions for Engineer&#039;s Office-Indirect Costs

2021-10-02 15:49:26.595636
Old Total Allocation: 643194.68: New Total Allocation: 746400 : Task: 16766 : Description: Allow for payment to Timber Coorporation-Indirect Costs

2021-10-02 15:49:26.657674
Old Total Allocation: 3110100.00: New Total Allocation: 3267600 : Task: 16770 : Description: Enbankment Filling  :Filling to proper levels and lines with approved imported material (Type 01) other than topsoil or artificial obstruction.-Material

2021-10-02 15:49:26.701866
Old Total Allocation: 292425.34: New Total Allocation: 324027.5 : Task: 16773 : Description: Drainage Crossings: 8m length &amp; 2m width Box type culvert-Material

2021-10-02 15:49:26.733888
Old Total Allocation: 202000.00: New Total Allocation: 274530 : Task: 16775 : Description: Drainage Crossings: 500mm internal bottom width, 1000 mm internal top width &amp; 1m depth (100mm thk) drainage crossing-Material

2021-10-02 15:49:26.819209
Old Total Allocation: 186875.00: New Total Allocation: 66875 : Task: 16781 : Description: Fencing work: Supply and erection of peripheral fence around the site with green colour PVC coated wire mesh (Gauge-8) -Sub Contract Payment

2021-10-02 15:49:27.306867
Old Total Allocation: 0.00: New Total Allocation: 239750.13 : Task: 16813 : Description: HEAD OFFICE OVERHEAD

2021-10-02 15:49:29.739678
Old Total Allocation: 9842.02: New Total Allocation: 11700 : Task: 16996 : Description: Mass Concrete (Grade 10) 75mm thick, 1:3:6 (40) screed concreting.-Material

2021-10-02 15:49:29.762060
Old Total Allocation: 59872.28: New Total Allocation: 71175 : Task: 16997 : Description: Reinforced Concrete (Grade 25) - Concreting column bases (300mm thick)-Material

2021-10-02 15:49:29.792681
Old Total Allocation: 34802.52: New Total Allocation: 40325 : Task: 16999 : Description: Reinforced Concrete (Grade 25) -Concreting columns from ground level 0 upto level 1-Material

2021-10-02 15:49:29.951619
Old Total Allocation: 275000.00: New Total Allocation: 557115 : Task: 17012 : Description:  20mm dia. Tor steel-Material

2021-10-02 15:49:29.971036
Old Total Allocation: 85800.00: New Total Allocation: 180125 : Task: 17013 : Description:  16mm dia. Tor steel-Material

2021-10-02 15:49:29.989387
Old Total Allocation: 0.00: New Total Allocation: 79030 : Task: 17014 : Description: 12mm dia. Tor steel-Material

2021-10-02 15:49:30.20654
Old Total Allocation: 0.00: New Total Allocation: 63000 : Task: 17016 : Description: 6mm dia. Mild steel -Material

2021-10-02 15:49:31.185597
Old Total Allocation: 39750.00: New Total Allocation: 17250 : Task: 17112 : Description: Wrought formwork -&#039;in Soffit of base slab.-Sub Contract Payment

2021-10-02 15:49:32.349650
Old Total Allocation: 7344.30: New Total Allocation: 3250 : Task: 17202 : Description: Wrought formwork -&#039;in Soffit of base slab.-Machinery

2021-10-02 15:49:35.373343
Old Total Allocation: 0.00: New Total Allocation: 31250 : Task: 17446 : Description: 10 mm dia.to 25 mm dia Tor steel bar-Material

2021-10-02 15:49:35.404313
Old Total Allocation: 0.00: New Total Allocation: 8000 : Task: 17448 : Description: Painting cement plaster general surface width exceeding 300 mm plain surface with one coat primer and two coats weather shield paint -Material

2021-10-02 15:49:35.573228
Old Total Allocation: 81524.13: New Total Allocation: 105000 : Task: 17462 : Description: Reinforced Concrete(Grade 35A)-400 mm Thickness Concrete for Base Slab-Material

2021-10-02 15:49:35.628778
Old Total Allocation: 0.00: New Total Allocation: 31250 : Task: 17466 : Description: High yield steel bar reinforcement-Wall-Material

2021-10-02 15:49:35.686339
Old Total Allocation: 0.00: New Total Allocation: 784000 : Task: 17470 : Description: 8mm-4mm Filter Media-Material

2021-10-02 15:49:36.313351
Old Total Allocation: 177436.18: New Total Allocation: 230385 : Task: 17523 : Description: 150mm x 150mm x 250mm Grade 20 concrete blocks-Sub Contract Payment

2021-10-02 15:49:36.333992
Old Total Allocation: 0.00: New Total Allocation: 259325 : Task: 17524 : Description: Fixing, 100 mm Thickness, Grade 30 Reinforced Pre Cast Concret Slab False, Size of Slab False 800mm x 800 mm-Sub Contract Payment

2021-10-02 15:49:38.391548
Old Total Allocation: 165651.86: New Total Allocation: 241800 : Task: 17689 : Description: Straight Specials : 100 mm dia Double Flange  DI Pipe piece 2000mm long. for culvert crossings-Material

2021-10-02 15:49:38.458474
Old Total Allocation: 0.00: New Total Allocation: 103200 : Task: 17694 : Description: Straight Specials : 80mm dia. DI Double Flange Pipe piece 1200mm long with Integrally Cast Puddle flange at 400mm from flange end. for section valves-Material

2021-10-02 15:49:38.488593
Old Total Allocation: 92527.07: New Total Allocation: 98000 : Task: 17696 : Description: 80mm Dia DI Coupling to suit 90 mm dia PVC pipe.for washouts-Material

2021-10-02 15:49:38.542547
Old Total Allocation: 0.00: New Total Allocation: 200840 : Task: 17700 : Description: 80 mm dia. Sluice Valve. for washouts-Material

2021-10-02 15:49:38.758263
Old Total Allocation: 0.00: New Total Allocation: 520213.54 : Task: 17717 : Description: PVC Type 600 Pipes 90mm dia.-Material

2021-10-02 15:49:38.776050
Old Total Allocation: 466750.00: New Total Allocation: 1197090.74 : Task: 17718 : Description: PVC Type 600 Pipes 110mm dia.-Material

2021-10-02 15:49:38.793576
Old Total Allocation: 126100.00: New Total Allocation: 527567.36 : Task: 17719 : Description: PVC Type 600 Pipes 160mm dia.-Material

2021-10-02 15:49:42.414306
Old Total Allocation: 38141.28: New Total Allocation: 12606.5 : Task: 18002 : Description: Gas Cylinder Gas distribution header

2021-10-02 15:49:42.457155
Old Total Allocation: 27561.16: New Total Allocation: 20513.16 : Task: 18005 : Description: flexible hose connection with accessories

2021-10-02 15:49:42.475862
Old Total Allocation: 32166.70: New Total Allocation: 11057 : Task: 18006 : Description: Internal wiring

2021-10-02 15:49:42.493906
Old Total Allocation: 71276.48: New Total Allocation: 71276.48 : Task: 18007 : Description: Solenoid Cut-off valves 20mm

2021-10-02 15:49:42.510895
Old Total Allocation: 111302.00: New Total Allocation: 20459 : Task: 18008 : Description: Ring type 2 gang switch

2021-10-02 15:49:42.563713
Old Total Allocation: 25810.00: New Total Allocation: 25814 : Task: 18012 : Description: 15mm G.I pipes with munting brackes and all requir

2021-10-02 15:49:42.617829
Old Total Allocation: 10303.52: New Total Allocation: 200 : Task: 18016 : Description: 40mm G.I pipes with mounting brackets and all req

2021-10-02 15:49:42.687027
Old Total Allocation: 4501.00: New Total Allocation: 101 : Task: 18021 : Description: 65mm dia Motorized valves

2021-10-02 15:49:43.78409
Old Total Allocation: 10000.00: New Total Allocation: 26500 : Task: 18054 : Description: Gas meter

2021-10-02 15:49:43.438221
Old Total Allocation: 59203.19: New Total Allocation: 59203.19 : Task: 18084 : Description: Gas Pipe Distribution

2021-10-02 15:49:43.513839
Old Total Allocation: 15000.00: New Total Allocation: 15048 : Task: 18088 : Description: IP42 DUCT/Ceiling

2021-10-02 15:49:43.544134
Old Total Allocation: 0.00: New Total Allocation: 35000 : Task: 18090 : Description: 230VAC N/C solenoid shut off valves

2021-10-02 15:49:43.621185
Old Total Allocation: 45000.00: New Total Allocation: 45060 : Task: 18096 : Description: flexible connection and gas cock

2021-10-02 15:49:43.668376
Old Total Allocation: 134384.78: New Total Allocation: 127471.04 : Task: 18099 : Description: Accessories

2021-10-02 15:49:46.76608
Old Total Allocation: 45213.44: New Total Allocation: 45267.44 : Task: 18286 : Description: 100mm GI heavy duty pipes

2021-10-02 15:49:46.95484
Old Total Allocation: 13412.83: New Total Allocation: 13454.83 : Task: 18287 : Description: 65mm Gi heavy duty pipes

2021-10-02 15:49:46.113313
Old Total Allocation: 15750.00: New Total Allocation: 3 : Task: 18288 : Description: 25mm dia GI heavy duty pipes

2021-10-02 15:49:46.262270
Old Total Allocation: 12421.18: New Total Allocation: 12425.18 : Task: 18300 : Description: 100mm dia gate valve

2021-10-02 15:49:46.281165
Old Total Allocation: 1.00: New Total Allocation: 3 : Task: 18301 : Description: 65mm dia gate valve

2021-10-02 15:49:46.358728
Old Total Allocation: 29048.18: New Total Allocation: 31448.18 : Task: 18307 : Description: Pipe fittings and accessories

2021-10-02 15:49:46.636697
Old Total Allocation: 20276.25: New Total Allocation: 25 : Task: 18330 : Description: 40mm dia Gi pipe

2021-10-02 15:49:46.921337
Old Total Allocation: 55822.07: New Total Allocation: 48085.31 : Task: 18354 : Description: Accessories

2021-10-02 15:49:47.690504
Old Total Allocation: 1062590.42: New Total Allocation: 1389800 : Task: 18411 : Description: Miscellaneous

2021-10-02 15:49:47.793637
Old Total Allocation: 145000.00: New Total Allocation: 190000 : Task: 18419 : Description: Miscellaneous

2021-10-02 15:49:47.822778
Old Total Allocation: 0.00: New Total Allocation: 8800 : Task: 18421 : Description: Miscellaneous

2021-10-02 15:49:49.913593
Old Total Allocation: 423435.50: New Total Allocation: 270500 : Task: 18586 : Description: Supply and Installation DI Pipe and Fittings-Material

2021-10-02 15:49:50.227925
Old Total Allocation: 174000.00: New Total Allocation: 249000 : Task: 18611 : Description: Concrete work-Material

2021-10-02 15:49:50.322454
Old Total Allocation: 25050.00: New Total Allocation: 24750 : Task: 18618 : Description: form work-Material

2021-10-02 15:49:53.165864
Old Total Allocation: 0.00: New Total Allocation: 6000 : Task: 18830 : Description: Fenial  Mounting-Material

2021-10-02 15:49:55.789349
Old Total Allocation: 0.00: New Total Allocation: 9321 : Task: 19045 : Description: Reinforcement work-Material

2021-10-02 15:49:55.877159
Old Total Allocation: 100000.00: New Total Allocation: 139680 : Task: 19052 : Description: Sub-Contractor Charges -Sub Contract Payment

2021-10-02 15:49:55.896091
Old Total Allocation: 100000.00: New Total Allocation: 108485.4 : Task: 19053 : Description: Supply and installation of ZN-AL Rofing sheet-Material

2021-10-02 15:49:55.970421
Old Total Allocation: 0.00: New Total Allocation: 33700 : Task: 19059 : Description: Gypsum grid ceiling-Material

2021-10-02 15:49:56.124854
Old Total Allocation: 450665.29: New Total Allocation: 505200 : Task: 19072 : Description: Solar Module-Material

2021-10-02 15:49:56.310412
Old Total Allocation: 1174104.49: New Total Allocation: 1205465.14 : Task: 19087 : Description: Office Maintenance-Preliminary

2021-10-02 15:49:58.845507
Old Total Allocation: 4014.19: New Total Allocation: 4014.19 : Task: 19287 : Description: Other Fixing Accessories-Material

2021-10-02 15:49:59.188145
Old Total Allocation: 14145.83: New Total Allocation: 14145.83 : Task: 19315 : Description: Power Cable-Material

2021-10-02 15:49:59.217425
Old Total Allocation: 32891.34: New Total Allocation: 32891.34 : Task: 19317 : Description: Other Fixing Accessories-Material

2021-10-02 15:50:00.365302
Old Total Allocation: 49793.51: New Total Allocation: 63793.51 : Task: 19411 : Description: Equipment Maintenance

2021-10-02 15:50:02.827523
Old Total Allocation: 318707.42: New Total Allocation: 318707.42 : Task: 19586 : Description: Sub-Contractor Charges -Sub Contract Payment

2021-10-02 15:50:02.871399
Old Total Allocation: 123385.29: New Total Allocation: 125020.43 : Task: 19589 : Description: Reinforcement work

2021-10-02 15:50:02.890213
Old Total Allocation: 181500.00: New Total Allocation: 355745.9 : Task: 19590 : Description: Reinforcement work

2021-10-02 15:50:02.910822
Old Total Allocation: 0.00: New Total Allocation: 681.62 : Task: 19591 : Description: Reinforcement work

2021-10-02 15:50:03.227516
Old Total Allocation: 80000.00: New Total Allocation: 266740.34 : Task: 19616 : Description: Reinforcement work-Material

2021-10-02 15:50:03.247339
Old Total Allocation: 0.00: New Total Allocation: 65.54 : Task: 19617 : Description: Reinforcement work-Material

2021-10-02 15:50:05.68945
Old Total Allocation: 170000.00: New Total Allocation: 2494500 : Task: 19762 : Description: Supply and Installation DI Pipe and Fittings

2021-10-02 15:50:08.825257
Old Total Allocation: 50000.00: New Total Allocation: 70000 : Task: 20047 : Description: Miscellaneous

2021-10-02 15:50:09.409516
Old Total Allocation: 26840.00: New Total Allocation: 18600 : Task: 20095 : Description: Miscellaneous-Sub Contract Payment

2021-10-02 15:50:09.463528
Old Total Allocation: 0.00: New Total Allocation: 53.24 : Task: 20099 : Description: Reinforcement work-Material

2021-10-02 15:50:09.482302
Old Total Allocation: 0.00: New Total Allocation: 589.86 : Task: 20100 : Description: Reinforcement work-Material

2021-10-02 15:50:10.609477
Negative allocation found: -55000.00 : Task: 20189 : Description: Consumables-Machinery

2021-10-02 15:50:12.669028
Old Total Allocation: 1221567.49: New Total Allocation: 1217323.49 : Task: 20312 : Description: Conduits Work

2021-10-02 15:50:15.910752
Old Total Allocation: 19210.00: New Total Allocation: 23050 : Task: 20558 : Description: PIPE-Material

2021-10-02 15:50:15.930745
Old Total Allocation: 4638.15: New Total Allocation: 3440.35 : Task: 20559 : Description: PIPE FIRRINGS-Material

2021-10-02 15:50:15.950311
Old Total Allocation: 86510.00: New Total Allocation: 128360 : Task: 20560 : Description: Valves-Material

2021-10-02 15:50:15.982292
Old Total Allocation: 670.22: New Total Allocation: 1588.22 : Task: 20562 : Description: Accessories-Material

2021-10-02 15:50:16.725091
Old Total Allocation: 495000.00: New Total Allocation: 435000 : Task: 20622 : Description: Rock Blasting-Stage 1 
-Sub Contract Payment

2021-10-02 15:50:16.745835
Old Total Allocation: 271333.24: New Total Allocation: 262000 : Task: 20623 : Description: ABC filling under floors
-Material

2021-10-02 15:50:16.886227
Old Total Allocation: 0.00: New Total Allocation: 253000 : Task: 20634 : Description: Reinforcement for column Shaft
-Material

2021-10-02 15:50:17.44187
Old Total Allocation: 155000.00: New Total Allocation: 117600 : Task: 20645 : Description: Base Concreting
-Material

2021-10-02 15:50:17.111888
Old Total Allocation: 0.00: New Total Allocation: 19000 : Task: 20650 : Description: Column Concreting
-Machinery

2021-10-02 15:50:17.160858
Old Total Allocation: 0.00: New Total Allocation: 90510 : Task: 20653 : Description: Random rubble masonry in foundation in 1:5 cement &amp; sand moter.-Material

2021-10-02 15:50:17.203240
Old Total Allocation: 0.00: New Total Allocation: 72000 : Task: 20656 : Description: Leveling the floor with imported soil
-Material

2021-10-02 15:50:17.221509
Old Total Allocation: 250000.00: New Total Allocation: 503000 : Task: 20657 : Description: Reinforcement work-Material

2021-10-02 15:50:17.276532
Old Total Allocation: 570426.86: New Total Allocation: 891130 : Task: 20661 : Description: Small Tools &amp; Tools Maintenance-Tool

2021-10-02 15:50:17.306709
Old Total Allocation: 2797.99: New Total Allocation: 20 : Task: 20663 : Description: Backfilling with approved  material-Sub Contract Payment

2021-10-02 15:50:17.700193
Old Total Allocation: 56128.93: New Total Allocation: 54372 : Task: 20689 : Description: Material-Material

2021-10-02 15:50:17.866558
Old Total Allocation: 56289.13: New Total Allocation: 56289.13 : Task: 20702 : Description: Copper Tape-Material

2021-10-02 15:50:18.189940
Old Total Allocation: 41197.12: New Total Allocation: 41197.12 : Task: 20724 : Description: Mild Steel-Material

2021-10-02 15:50:20.85970
Old Total Allocation: 2813.14: New Total Allocation: 2813.14 : Task: 20870 : Description: End clamp-Material

2021-10-02 15:50:20.395665
Old Total Allocation: 0.00: New Total Allocation: 1600 : Task: 20893 : Description: Concreting in Beam-Machinery

2021-10-02 15:50:20.417613
Old Total Allocation: 1528907.06: New Total Allocation: 1485000 : Task: 20894 : Description: Concreting in Beam-Material

2021-10-02 15:50:20.476841
Old Total Allocation: 332500.00: New Total Allocation: 427500 : Task: 20898 : Description: Reinforcement work-Material

2021-10-02 15:50:20.507960
Old Total Allocation: 70000.00: New Total Allocation: 264000 : Task: 20900 : Description: Grade 25 Reinforced Concrete-Machinery

2021-10-02 15:50:20.527153
Old Total Allocation: 2140469.88: New Total Allocation: 2079000 : Task: 20901 : Description: Grade 25 Reinforced Concrete-Material

2021-10-02 15:50:20.546281
Old Total Allocation: 154999.91: New Total Allocation: 165000 : Task: 20902 : Description: Grade 25 Reinforced Concrete-Sub Contract Payment

2021-10-02 15:50:20.565376
Old Total Allocation: 0.00: New Total Allocation: 3375000 : Task: 20903 : Description: Reinforcement work-Material

2021-10-02 15:50:21.666640
Old Total Allocation: 0.00: New Total Allocation: 300 : Task: 20990 : Description: 25mm dia SCH 80 pipe-Material

2021-10-02 15:50:21.688637
Old Total Allocation: 0.00: New Total Allocation: 3000 : Task: 20991 : Description: 1st regulator-Material

2021-10-02 15:50:21.708745
Old Total Allocation: 2732.28: New Total Allocation: 2700 : Task: 20992 : Description: pigtail hose-Material

2021-10-02 15:50:21.727728
Old Total Allocation: 1150.00: New Total Allocation: 2200 : Task: 20993 : Description: pressure gauge-Material

2021-10-02 15:50:21.746175
Old Total Allocation: 1596.29: New Total Allocation: 1600 : Task: 20994 : Description: Cylinder coupling-Material

2021-10-02 15:50:21.763600
Old Total Allocation: 1221.85: New Total Allocation: 1200 : Task: 20995 : Description: 1/4&#039;&#039; valve-Material

2021-10-02 15:50:21.781134
Old Total Allocation: 3372.34: New Total Allocation: 3200 : Task: 20996 : Description: 1/2&#039;&#039; ball valve-Material

2021-10-02 15:50:21.811291
Old Total Allocation: 1686.17: New Total Allocation: 1600 : Task: 20998 : Description: 15mm ball valve-Material

2021-10-02 15:50:21.828635
Old Total Allocation: 3278.60: New Total Allocation: 3400 : Task: 20999 : Description: KLS 5-Material

2021-10-02 15:50:21.858004
Old Total Allocation: 0.00: New Total Allocation: 12500 : Task: 21001 : Description: IP 65 Detectors-Material

2021-10-02 15:50:21.876815
Old Total Allocation: 11200.00: New Total Allocation: 14500 : Task: 21002 : Description: 1/2&#039;&#039; Solenoid valve-Material

2021-10-02 15:50:21.897610
Old Total Allocation: 0.00: New Total Allocation: 3000 : Task: 21003 : Description: Emergency stop switch-Material

2021-10-02 15:50:21.916512
Old Total Allocation: 443.60: New Total Allocation: 550 : Task: 21004 : Description: 0.5sqmm 3 core cable-Material

2021-10-02 15:50:21.935914
Old Total Allocation: 2490.00: New Total Allocation: 3000 : Task: 21005 : Description: 0.5sqmm 2 core cable-Material

2021-10-02 15:50:21.956018
Old Total Allocation: 4415.56: New Total Allocation: 1490 : Task: 21006 : Description: Conduits-Material

2021-10-02 15:50:21.974999
Old Total Allocation: 0.00: New Total Allocation: 1 : Task: 21007 : Description: Other Items-Material

2021-10-02 15:50:22.474852
Old Total Allocation: 131360.00: New Total Allocation: 230312 : Task: 21046 : Description: Supply and installation of Steel Truss for roof

2021-10-02 15:50:23.483638
Old Total Allocation: 68900.00: New Total Allocation: 1689650 : Task: 21122 : Description: Reinforcement work

2021-10-02 15:50:24.841290
Old Total Allocation: 1266395.48: New Total Allocation: 1266395.48 : Task: 21223 : Description: Point Wiring

2021-10-02 15:50:24.919707
Old Total Allocation: 159861.15: New Total Allocation: 159861.15 : Task: 21229 : Description: Labour-DO NOT USE

2021-10-02 15:50:26.489895
Old Total Allocation: 50000.00: New Total Allocation: 56000 : Task: 21343 : Description: Supplying and application of internal wall painting-3 coat system

2021-10-02 15:50:27.145084
Old Total Allocation: 34287.05: New Total Allocation: 34287.05 : Task: 21397 : Description: Other Fixing Accessories-Material

2021-10-02 15:50:28.229645
------------------Script Completed----------------------------

2021-10-02 15:53:12.579547
==================Script Sarted==========================

2021-10-02 15:53:12.624240
8870 records selected

2021-10-02 15:53:15.7765
Old Total Allocation: 57881.01: New Total Allocation: 57881.01 : Task: 21578 : Description: GI Pole with Ni-lone Bar/Base-Material

2021-10-02 15:53:15.260551
Old Total Allocation: 2107.64: New Total Allocation: 2107.64 : Task: 21597 : Description: Other Fixing Accessories-Material

2021-10-02 15:53:21.248013
Old Total Allocation: 2649.68: New Total Allocation: 2649.68 : Task: 22045 : Description: Other Fixing Accessories-Material

2021-10-02 15:53:22.149486
Old Total Allocation: 6859.98: New Total Allocation: 6859.98 : Task: 22118 : Description: Other Fixing Accessories-Material

2021-10-02 15:53:22.759740
Old Total Allocation: 16850.00: New Total Allocation: 10200048.67 : Task: 22164 : Description: Supply  UPVC/PVC Pipe And Fitiings

2021-10-02 15:53:22.781861
Old Total Allocation: 2169750.00: New Total Allocation: 11254426.76 : Task: 22165 : Description: Supply DI Pipe and Fittings

2021-10-02 15:53:23.118131
Old Total Allocation: 857500.00: New Total Allocation: 863500 : Task: 22191 : Description: Grade 25 Reinforced Concrete

2021-10-02 15:53:23.164919
Old Total Allocation: 683580.61: New Total Allocation: 537050 : Task: 22194 : Description: Concreting in Beam

2021-10-02 15:53:23.186089
Old Total Allocation: 56279.53: New Total Allocation: 43750 : Task: 22195 : Description: Grade 25 Reinforced Concrete

2021-10-02 15:53:23.238733
Old Total Allocation: 24117.60: New Total Allocation: 17840 : Task: 22198 : Description: Supply and installation of Sandwitch pannel roofing sheet

2021-10-02 15:53:23.258099
Old Total Allocation: 404537.08: New Total Allocation: 60750 : Task: 22199 : Description: Supply and installation of Steel Truss for roof

2021-10-02 15:53:24.186827
Old Total Allocation: 189251.71: New Total Allocation: 189240 : Task: 22259 : Description: 100mm dia HD GI pipe-Material

2021-10-02 15:53:24.208910
Old Total Allocation: 509.26: New Total Allocation: 2 : Task: 22260 : Description: 50mm dia HD GI Pipe-Material

2021-10-02 15:53:24.226914
Old Total Allocation: 0.00: New Total Allocation: 5 : Task: 22261 : Description: 32mm dia HD GI Pipe-Material

2021-10-02 15:53:24.246850
Old Total Allocation: 0.00: New Total Allocation: 2 : Task: 22262 : Description: 20mm dia HD GI Pipe-Material

2021-10-02 15:53:24.267797
Old Total Allocation: 5089.28: New Total Allocation: 3 : Task: 22263 : Description: 25mm dia Gate valve-Material

2021-10-02 15:53:24.287289
Old Total Allocation: 0.00: New Total Allocation: 5 : Task: 22264 : Description: 50mm dia gate valve-Material

2021-10-02 15:53:24.308473
Old Total Allocation: 53400.00: New Total Allocation: 3 : Task: 22265 : Description: 100mm dia gate valve-Material

2021-10-02 15:53:24.341889
Old Total Allocation: 0.00: New Total Allocation: 11670 : Task: 22266 : Description: 100mm dia butter fly valve-Material

2021-10-02 15:53:24.386949
Old Total Allocation: 0.00: New Total Allocation: 16301 : Task: 22267 : Description: 100mm dia non return valve-Material

2021-10-02 15:53:24.412398
Old Total Allocation: 2.00: New Total Allocation: 3 : Task: 22268 : Description: 100mm dia strainer-Material

2021-10-02 15:53:24.438342
Old Total Allocation: 4.00: New Total Allocation: 6 : Task: 22269 : Description: 50mm dia strainer-Material

2021-10-02 15:53:24.703758
Old Total Allocation: 253450.08: New Total Allocation: 210147.85 : Task: 22286 : Description: Fittings and accessories-Material

2021-10-02 15:53:25.478912
Old Total Allocation: 316000.00: New Total Allocation: 240000 : Task: 22338 : Description: Concreting in suspended Slab

2021-10-02 15:53:25.937760
Old Total Allocation: 189400.00: New Total Allocation: 196000 : Task: 22374 : Description: Form Working

2021-10-02 15:53:26.327951
Old Total Allocation: 348619.08: New Total Allocation: 301000 : Task: 22401 : Description: Concreting in suspended Slab

2021-10-02 15:53:26.440968
Old Total Allocation: 15000.00: New Total Allocation: 52800 : Task: 22407 : Description: Miscellaneous

2021-10-02 15:53:26.879200
Old Total Allocation: 184489.36: New Total Allocation: 125000 : Task: 22437 : Description: Grade 25 Reinforced Concrete

2021-10-02 15:53:26.897489
Old Total Allocation: 13750.00: New Total Allocation: 32250 : Task: 22438 : Description: Grade 25 Reinforced Concrete

2021-10-02 15:53:27.162634
Old Total Allocation: 0.00: New Total Allocation: 1000 : Task: 22457 : Description: Concreting in suspended Slab

2021-10-02 15:53:27.944610
Old Total Allocation: 15.00: New Total Allocation: 17 : Task: 22511 : Description: 63mm gate valve-Material

2021-10-02 15:53:28.228563
Old Total Allocation: 1610000.00: New Total Allocation: 140000 : Task: 22525 : Description: Miscellaneous

2021-10-02 15:53:28.248920
Old Total Allocation: 2847.36: New Total Allocation: 12 : Task: 22526 : Description: 25mm dia upvc pnt 11-Material

2021-10-02 15:53:28.271364
Old Total Allocation: 1403.00: New Total Allocation: 10 : Task: 22527 : Description: 20mm dia upvc pnt 11-Material

2021-10-02 15:53:28.445741
Old Total Allocation: 84405.59: New Total Allocation: 84125 : Task: 22540 : Description:  Fittings &amp; Accessories-Material

2021-10-02 15:53:28.568642
Old Total Allocation: 99599.29: New Total Allocation: 99599.29 : Task: 22547 : Description: float / others

2021-10-02 15:53:28.653635
Old Total Allocation: 64550.00: New Total Allocation: 80800 : Task: 22551 : Description: Miscellaneous

2021-10-02 15:53:28.673385
Old Total Allocation: 317460.29: New Total Allocation: 247500 : Task: 22552 : Description: Miscellaneous

2021-10-02 15:53:28.734206
Old Total Allocation: 16625.00: New Total Allocation: 22500 : Task: 22553 : Description: Miscellaneous

2021-10-02 15:53:29.268846
Old Total Allocation: 24000.00: New Total Allocation: 502970 : Task: 22594 : Description: LPG Vapour out Pipe line Tanks to Pressure Regula-Material

2021-10-02 15:53:29.300595
Old Total Allocation: 302760.00: New Total Allocation: 532760 : Task: 22596 : Description: Tanks Liquid Out Lines to Vapourizes:-Material

2021-10-02 15:53:29.320813
Old Total Allocation: 0.00: New Total Allocation: 587760 : Task: 22597 : Description: Vapour Line (Vapourizers to Regulator Station)-Material

2021-10-02 15:53:34.478723
Old Total Allocation: 1348880.00: New Total Allocation: 2146180 : Task: 23004 : Description: Cost for Di pipe and Fitting as per the Boq Qty

2021-10-02 15:53:34.524730
Old Total Allocation: 2544432.00: New Total Allocation: 2556682 : Task: 23007 : Description: Overhead-General Overhead

2021-10-02 15:53:34.544029
Old Total Allocation: 420000.00: New Total Allocation: 1281750 : Task: 23008 : Description: Building Material

2021-10-02 15:53:35.787937
Old Total Allocation: 6193.80: New Total Allocation: 36500 : Task: 23100 : Description: 110mm dia upvc pnt 7-Material

2021-10-02 15:53:37.214916
Old Total Allocation: 23982.89: New Total Allocation: 23982.89 : Task: 23200 : Description: Printing &amp; Stationery

2021-10-02 15:53:37.666405
Old Total Allocation: 2319.04: New Total Allocation: 2319.04 : Task: 23237 : Description: Printing &amp; Stationery

2021-10-02 15:53:37.728914
Old Total Allocation: 1007.61: New Total Allocation: 1007.61 : Task: 23241 : Description: Document Charges

2021-10-02 15:53:38.137744
Old Total Allocation: 85350.00: New Total Allocation: 3000 : Task: 23274 : Description: Travelling and Transport

2021-10-02 15:53:39.807417
Old Total Allocation: 238090.60: New Total Allocation: 238090.6 : Task: 23403 : Description: Civil cost-Material

2021-10-02 15:53:40.103941
Old Total Allocation: 43131.34: New Total Allocation: 43131.34 : Task: 23426 : Description: Material

2021-10-02 15:53:40.137372
Old Total Allocation: 102280.75: New Total Allocation: 102305.75 : Task: 23428 : Description: Equipment Maintenance

2021-10-02 15:53:40.467146
Old Total Allocation: 19482.65: New Total Allocation: 14741 : Task: 23454 : Description: Plumbing Pipe Fittings &amp; Accessories-Material

2021-10-02 15:53:41.971281
Old Total Allocation: 24800.00: New Total Allocation: 1071880 : Task: 23569 : Description: Stock Control

2021-10-02 15:53:43.741505
Old Total Allocation: 23818.98: New Total Allocation: 24800 : Task: 23705 : Description: Printing &amp; Stationery

2021-10-02 15:53:44.10234
Old Total Allocation: 133375.68: New Total Allocation: 124380 : Task: 23726 : Description: Backfilling with approved  material

2021-10-02 15:53:44.106446
Old Total Allocation: 247275.08: New Total Allocation: 267600 : Task: 23731 : Description: 2&quot; tk grade 15 screed concrete 

2021-10-02 15:53:44.127643
Old Total Allocation: 1391277.87: New Total Allocation: 1393350 : Task: 23732 : Description: Miscellaneous Concrete Works

2021-10-02 15:53:44.146809
Old Total Allocation: 157186.64: New Total Allocation: 171075 : Task: 23733 : Description: Grade 25 Reinforced Concrete

2021-10-02 15:53:44.166151
Old Total Allocation: 198897.97: New Total Allocation: 226068.4 : Task: 23734 : Description: Form Working

2021-10-02 15:53:44.186786
Old Total Allocation: 599853.37: New Total Allocation: 434000 : Task: 23735 : Description: Reinforcement work

2021-10-02 15:53:44.236085
Old Total Allocation: 80430.97: New Total Allocation: 70350 : Task: 23738 : Description: Miscellaneous

2021-10-02 15:53:45.109711
Old Total Allocation: 350285.00: New Total Allocation: 260218 : Task: 23804 : Description: Light Fittings-Material

2021-10-02 15:53:45.152573
Old Total Allocation: 33300.00: New Total Allocation: 9 : Task: 23807 : Description: Conduits-Material

2021-10-02 15:53:45.187255
Old Total Allocation: 36213.66: New Total Allocation: 36215.66 : Task: 23809 : Description: Panel Boards-Material

2021-10-02 15:53:46.143232
Old Total Allocation: 314829.00: New Total Allocation: 314836 : Task: 23877 : Description: Fire items-Material

2021-10-02 15:53:47.143249
Old Total Allocation: 60014.93: New Total Allocation: 11252.8 : Task: 23955 : Description: Supply and fix 100x100mm size 0.47mm tk. Colour bo

2021-10-02 15:53:47.224229
Old Total Allocation: 1257910.00: New Total Allocation: 1281000 : Task: 23960 : Description: Supply and fix 4mm tk. Aluminum composite sheet (A

2021-10-02 15:53:47.622195
Old Total Allocation: 67968.24: New Total Allocation: 67968.24 : Task: 23992 : Description: Conduits Materials-Material

2021-10-02 15:53:47.923387
Old Total Allocation: 0.00: New Total Allocation: 142728.04 : Task: 24008 : Description: Distribution Boards-Material

2021-10-02 15:53:48.404825
Old Total Allocation: 2869100.14: New Total Allocation: 2869100.14 : Task: 24042 : Description: Point Wiring-Material

2021-10-02 15:53:48.450242
Old Total Allocation: 1420394.33: New Total Allocation: 1411083.13 : Task: 24043 : Description: Conduiting material-Material

2021-10-02 15:53:48.557072
Old Total Allocation: 689994.45: New Total Allocation: 686397.45 : Task: 24051 : Description: Preliminaries-Preliminary

2021-10-02 15:53:48.640644
Old Total Allocation: 3266200.00: New Total Allocation: 12186300 : Task: 24057 : Description: Panel Boards-Material

2021-10-02 15:53:48.747539
Old Total Allocation: 372973.51: New Total Allocation: 685666.51 : Task: 24061 : Description: Cable support system-Material

2021-10-02 15:53:50.264263
Old Total Allocation: 1411.41: New Total Allocation: 1411.41 : Task: 24167 : Description: Fenial/ESE Mounting-Material

2021-10-02 15:53:50.301503
Old Total Allocation: 4735.81: New Total Allocation: 4735.81 : Task: 24168 : Description: GI Pole with Ni-lone Bar/Base-Material

2021-10-02 15:53:51.127705
Old Total Allocation: 22080.00: New Total Allocation: 15670 : Task: 24234 : Description: Sigma Red/Sigma White-Material

2021-10-02 15:53:53.254942
Old Total Allocation: 5000.00: New Total Allocation: 8650 : Task: 24402 : Description: 16mm Tor bar-Material

2021-10-02 15:53:53.297743
Old Total Allocation: 0.00: New Total Allocation: 25750 : Task: 24405 : Description: 20mm Tor bar (For Column )-Material

2021-10-02 15:53:53.329264
Old Total Allocation: 0.00: New Total Allocation: 18250 : Task: 24407 : Description: 10mm Tor bar-Material

2021-10-02 15:53:53.819899
Old Total Allocation: 0.00: New Total Allocation: 22845 : Task: 24447 : Description: Carpet flooring work

2021-10-02 15:53:54.376496
Old Total Allocation: 19050.00: New Total Allocation: 18600 : Task: 24490 : Description: Equipment Maintenance

2021-10-02 15:53:56.81554
Old Total Allocation: 24516.40: New Total Allocation: 24516.4 : Task: 24602 : Description: MD&#039;s residence

2021-10-02 15:53:56.583967
Old Total Allocation: 0.00: New Total Allocation: 19600 : Task: 24643 : Description: Miscellaneous Concrete Works

2021-10-02 15:53:56.626774
Old Total Allocation: 158844.94: New Total Allocation: 192000 : Task: 24646 : Description: Miscellaneous Concrete Works

2021-10-02 15:53:56.852525
Old Total Allocation: 1436.16: New Total Allocation: 1436.16 : Task: 24664 : Description: Civil cost-Material

2021-10-02 15:53:59.955424
Old Total Allocation: 21084.25: New Total Allocation: 8019 : Task: 24886 : Description: Pipe &amp; Fittings-Material

2021-10-02 15:54:02.637184
Old Total Allocation: 396500.00: New Total Allocation: 1247900 : Task: 25091 : Description: Supply of sluice valves-Material

2021-10-02 15:54:02.674138
Old Total Allocation: 434000.00: New Total Allocation: 1166875 : Task: 25093 : Description: House connections

2021-10-02 15:54:02.747653
Old Total Allocation: 27500.00: New Total Allocation: 28500 : Task: 25098 : Description: Construction of Gate Valve Chamber

2021-10-02 15:54:04.999409
Old Total Allocation: 114420.49: New Total Allocation: 114420.49 : Task: 25269 : Description: Civil cost-Material

2021-10-02 15:54:07.623385
Old Total Allocation: 1440536.16: New Total Allocation: 1452500 : Task: 25467 : Description: Miscellaneous

2021-10-02 15:54:07.644301
Old Total Allocation: 2666609.31: New Total Allocation: 2812050 : Task: 25468 : Description: Grade 25 Reinforced Concrete

2021-10-02 15:54:07.664403
Old Total Allocation: 4136820.75: New Total Allocation: 1215050 : Task: 25469 : Description: Form Working

2021-10-02 15:54:07.719222
Old Total Allocation: 352100.00: New Total Allocation: 357100 : Task: 25472 : Description: Reinforcement work

2021-10-02 15:54:07.739436
Old Total Allocation: 837149.41: New Total Allocation: 832875 : Task: 25473 : Description: Miscellaneous

2021-10-02 15:54:07.759620
Old Total Allocation: 2967241.96: New Total Allocation: 2963557 : Task: 25474 : Description: Grade 25 Reinforced Concrete

2021-10-02 15:54:07.783482
Old Total Allocation: 10977128.42: New Total Allocation: 9617362.5 : Task: 25475 : Description: Form Working

2021-10-02 15:54:07.815807
Old Total Allocation: 6972000.00: New Total Allocation: 7340000 : Task: 25477 : Description: Reinforcement work

2021-10-02 15:54:08.422080
Old Total Allocation: 1251250.00: New Total Allocation: 1697500 : Task: 25518 : Description: Miscellaneous

2021-10-02 15:54:08.953447
Old Total Allocation: 3209.59: New Total Allocation: 23 : Task: 25554 : Description: Gas Pipe Distribution-Material

2021-10-02 15:54:12.901100
Old Total Allocation: 1485966.37: New Total Allocation: 1485966.37 : Task: 25833 : Description: Labour for laying 90mm dia. HDPE 3459m-Skill Labour

2021-10-02 15:54:14.245466
Old Total Allocation: 330000.00: New Total Allocation: 889000 : Task: 25931 : Description: VO.5.1

2021-10-02 15:54:14.277527
Old Total Allocation: 1185181.31: New Total Allocation: 2218694 : Task: 25933 : Description: Culvert Crossing

2021-10-02 15:54:16.731633
Old Total Allocation: 16331.89: New Total Allocation: 16331.89 : Task: 26099 : Description: Civil cost-Material

2021-10-02 15:54:17.487630
Old Total Allocation: 3995713.24: New Total Allocation: 3995713.24 : Task: 26160 : Description: Feeder Cable-Material

2021-10-02 15:54:24.540190
Old Total Allocation: 1094.86: New Total Allocation: 1094.86 : Task: 26721 : Description: Printing &amp; Stationery

2021-10-02 15:54:25.955152
Old Total Allocation: 8014.13: New Total Allocation: 8014.13 : Task: 26835 : Description: Printing &amp; Stationery

2021-10-02 15:54:26.683605
Old Total Allocation: 801446.76: New Total Allocation: 990414.2 : Task: 26886 : Description: Computer, printers 

2021-10-02 15:54:27.488661
Old Total Allocation: 95206.00: New Total Allocation: 96036 : Task: 26946 : Description: Staff Welfare

2021-10-02 15:54:33.120505
Old Total Allocation: 24716.66: New Total Allocation: 24716.66 : Task: 27371 : Description: Other Fixing Accessories-Material

2021-10-02 15:54:33.152136
Old Total Allocation: 0.00: New Total Allocation: 62100 : Task: 27373 : Description: Supply &amp; Installation of 5.5kg CO2 type fire extinguishers with metal brackets fixed on the wall/ fire cabinet. -Material

2021-10-02 15:54:33.171208
Old Total Allocation: 0.00: New Total Allocation: 80000 : Task: 27374 : Description: Supply &amp; Installation of 45kg DCP type fire extinguishers with metal brackets fixed on the wall/ fire cabinet. -Material

2021-10-02 15:54:33.253714
Old Total Allocation: 0.00: New Total Allocation: 200000 : Task: 27380 : Description: Supply and Installation of addresable fire alarm panel c/w mounting accessories.-Material

2021-10-02 15:54:33.320086
Old Total Allocation: 0.00: New Total Allocation: 30000 : Task: 27385 : Description: Supply &amp; Installation of photoluminous type fire exit sign board with battery backup-Material

2021-10-02 15:54:34.326871
Old Total Allocation: 0.00: New Total Allocation: 15100 : Task: 27465 : Description: Veepower Box-Material

2021-10-02 15:54:37.478723
Old Total Allocation: 28412.09: New Total Allocation: 28412.09 : Task: 27700 : Description: Civil cost-Material

2021-10-02 15:54:44.637216
Old Total Allocation: 13151.78: New Total Allocation: 13151.78 : Task: 28274 : Description: Copper Tape-Material

2021-10-02 15:54:48.193530
Old Total Allocation: 7576.37: New Total Allocation: 7576.37 : Task: 28542 : Description: Other Fixing Accessories-Material

2021-10-02 15:54:53.159550
Old Total Allocation: 8402.03: New Total Allocation: 8402.03 : Task: 28910 : Description: Other Fixing Accessories-Material

2021-10-02 15:55:02.835825
Old Total Allocation: 7087.48: New Total Allocation: 7087.48 : Task: 29673 : Description: DC Clips-Material

2021-10-02 15:55:08.247955
Old Total Allocation: 15212.78: New Total Allocation: 15212.78 : Task: 30105 : Description: Other-Indirect Costs

2021-10-02 15:55:10.516524
------------------Script Completed----------------------------

2021-10-02 15:58:51.647382
==================Script Sarted==========================

2021-10-02 15:58:51.654658
162 records selected

2021-10-02 15:58:53.847434
------------------Script Completed----------------------------